1 2
3 4
55
The Sapling Company, Inc.
1633 Republic Road
Huntingdon Valley, PA 19006
USA
P. (+1) 215.322.6063
F. (+1) 215.322.8498
www.sapling-inc.com
Double Mount Installation - Square Clock
1) Install the double gang box in the wall or ceiling.
If you are installing the gang box in the wall, leave
at least eleven inches between the top of the
gang box and the ceiling. If you are installing the
gang box in the ceiling, leave at least eleven inches
between the gang box and the wall. The box should
be installed level and plumb with the wall
and ceiling.
3) Detach the mounting plate from the mounting
pole by unscrewing the two screws. Set the screws
and pole aside for later.
2) Run power and communication wiring to the
gang box. See the sections of this manual labeled
“Wiring Information” for additional details,
depending on your system.
If you are using a 2-wire system, pull the
YELLOW and GREEN wires out of
the connectors.
4) Attach the mounting plate to the gang box using
only two of the four long, silver #6-32x1 screws.
With the mounting plate as a guide, use the pencil
to trace the locations of the four larger holes at the
outer corners.
Ceiling
11” Minimum
CHECK YOUR WIRING
The voltage between the white and black wires
should measure 105-126 volts AC in the 115
volt model, 207-253 volts AC in the 230 volt
model, or 21.5-26.5 volts AC in the 24
volt model.
If you are using the 24 volt model, make sure
that the wiring leading to the clock is from an
ISOLATED transformer.