Concrete curing function
When pipes of floor heating are installed, operation for reinforcing concrete curing is applied . (Period of operation: 20 days)
Entering procedure
1 . After turning off the DIP switch K3 (3rd switch of SW03) of control kit (Default ON), turn off and turn on the control kit . The
operation for concrete curing starts automatically . (If blackout occurs and communictation restarts later, operation will
continue .)
2 . Temperature of discharge water is controlled as time goes on like below .
Day
Temp.
0
10
20
30
40
50
60
1
2
3
4
5
6
7
8
9
10 11
12 13 14
15
16 17
18 19
20
Classification
Initial Heating
Step raise
Heating
Step down
Total
(Hour)
Time
96
48
24
24
24
168
24
24
48
480
Temperature
30
55
30
40
50
55
50
40
30
-
3 . Remaining days are displayed on the wired remote controller during operation but key operation is unavailable .
Remaining days
are displayed .
❋
❋
If an error is displayed, concrete curing function does not work .
42
EHS MONO Kit-EU_IM_05388A-00_EN.indd 42
2015-03-18 오전 11:53:55
Содержание MIM-E03*N
Страница 1: ...EHS MONO Kit EU_IM_05388A 00_EN indd 2 2015 03 18 오전 11 53 30 ...
Страница 32: ...Wiring schematics Wiring diagram 31 ENGLISH EHS MONO Kit EU_IM_05388A 00_EN indd 31 2015 03 18 오전 11 53 48 ...
Страница 46: ...MEMO 45 ENGLISH EHS MONO Kit EU_IM_05388A 00_EN indd 45 2015 03 18 오전 11 53 56 ...