Installation and operating instructions Salmson-Rocsan SDL 43
INSTALLATION English
and storage locations using the lifting equip-
ment. The machine must be positioned on a firm
bearing surface. For transporting the pump, the
load-carrying equipment must be secured to the
lifting eyelets provided. When using chains, they
must be connected with a shackle to the lifting
eyelets or the carrying handle. Lifting gear must
be technically approved.
• Power supply cables must be laid out in such
a way that safe operation and trouble-free
assembly/dismantling are possible at all times.
The pump must never be carried or dragged by
the power supply cable. Check whether the cable
present is long enough for its cross-section and
its installation type.
• When using switchgear, the corresponding
protection class must be observed. In general,
switchgear must be overflow-proof and is to be
installed outside potentially explosive areas.
• When used in an explosive atmosphere, it must
be ensured that the pump and all accessories are
approved for this purpose.
• Structural components and foundations must be
of sufficient stability in order to allow the product
to be fixed securely and functionally. The operator
or the supplier is responsible for provision of
the foundations and their suitability in terms of
dimensions, stability and strength.
• If the motor housing is to be taken out of the
fluid during operation, the operating mode for
non-immersed operation should be followed.
To keep dry motors sufficiently cooled in S3
mode, they must be flooded completely before
being switched back on if the motor has been
taken out of the fluid!
• Never let the pump run dry. The water level must
never fall below the minimum. Therefore, we
recommend installing a level control system or a
dry-running protection system where there are
great variations in the level.
•
Use guide and deflector plates for the fluid intake.
If the water jet reaches the surface of the water,
air will be introduced into the fluid, which can
accumulate in the pipe system. This can result in
inadmissible operating conditions and to deacti-
vation of the entire system.
• Check that the available planning documentation
(installation diagrams, layout of the operating
space, intake ratios) is complete and correct.
• Please observe all regulations, rules and legal
requirements for working with and underneath
heavy suspended loads. Wear appropriate protec-
tive clothing/equipment.
• Please also observe the applicable national acci-
dent prevention regulations and trade association
safety provisions.
5.3.1. Maintenance work
After a storage period of more than 6 months, the
following maintenance work must be carried out
before installation:
Check oil level in sealing chamber
The sealing chamber has a hole for draining and
filling the chamber.
1.
Position the pump horizontally on a firm surface
with the screw plug facing upward.
Make sure that the pump cannot fall over and/
or slip!
2. Unscrew the screw plug (see Fig. 7).
3. The oil should reach up to about 1 cm below the
hole for the screw plug.
4. If there is not enough oil in the sealing chamber,
top it up. To do so, follow the instructions under
"Oil change" in the "Maintenance and repair"
chapter.
5. Clean the screw plug, replace the joint ring, if
necessary, and screw it back in.
5.3.2. Stationary wet well installation
A suspension unit must be installed for wet
well installation. This must be ordered from the
manufacturer separately. The pipe system on the
pressure side is connected to this.
The connected pipe system must be self-sup-
porting, i.e. it may not be supported by the
suspension unit.
The operating space must be laid out so that the
suspension unit can be installed and operated
without difficulty.
If the motor emerges during operation, the
following operating parameters must be strictly
observed:
• The
max. fluid temperature and ambient tem
-
perature
is
40 °C
.
•
Details for "Non-immersed operating mode"
Fig. 2.: Wet well installation
1 Suspension unit
6a Min. water level for
immersed operation
2 Non-return valve
6b
Min. water level for
non-immersed oper-
ation
3 Gate valve
7 Impact protection plate
4 Pipe elbow
8 Inlet
5 Guide pipe (to be provided by the customer!)
A Minimum distances in parallel operation
W Minimum distances in alternating operation
Work steps
1.
Installation of the suspension unit: about 3-6 h
(please see the operating manual for the suspen-
sion unit).
2. Preparing the pump for operation on a suspension
unit: about 1-3 h
(please see the operating manual for the suspen-
sion unit).
3.
Installing the pump: about 3-5 h
•
Check that the suspension unit is firmly fixed
and functions properly.