7 Installation
Installer reference guide
29
RRLQ004~008CA + RHBH/X04+08CB
ROTEX HPSU low temperature Bi‑bloc
4P384979-1 – 2015.01
7.2.3
To open the indoor unit
1
Loosen and remove the 2 screws that fix the front panel.
2×
2
Tilt the front panel towards you and remove the front panel.
7.2.4
To open the switch box cover of the
indoor unit
4×
7.3
Mounting the outdoor unit
7.3.1
About mounting the outdoor unit
When
You have to mount the outdoor and indoor unit before you can
connect the refrigerant and water piping.
Typical workflow
Mounting the outdoor unit typically consists of the following stages:
1
Providing the installation structure.
2
Installing the outdoor unit.
3
Providing drainage.
4
Preventing the outdoor unit from falling over.
5
Protecting the unit against snow and wind by installing a snow
cover and baffle plates. See "Preparing installation site" in
7.3.2
Precautions when mounting the outdoor
unit
INFORMATION
Also read the precautions and requirements in the
following chapters:
▪ General safety precautions
▪ Preparation
7.3.3
To provide the installation structure
Check the strength and level of the installation ground so that the
unit will not cause any operating vibration or noise.
Fix the unit securely by means of foundation bolts in accordance
with the foundation drawing.
If the unit is installed directly on the floor, prepare 4 sets of M8 or
M10 anchor bolts, nuts and washers (field supply) as follows:
INFORMATION
The maximum height of the upper protruding part of the
bolts is 15 mm.
NOTICE
Fix the outdoor unit to the foundation bolts using nuts with
resin washers (a). If the coating on the fastening area is
stripped off, the nuts rust easily.
a
283
580
<100
(mm)
<100
>300
In any case, provide at least 300 mm of free space below the unit.
Additionally, make sure the unit is positioned at least 100 mm above
the maximum expected level of snow. In this case, it is
recommended to construct a pedestal, and on this pedestal install
the EKFT008CA option kit.