Prepare a high-lift (D) of sufficient
forks carrying capacity
- shift forks (G) under the machine,
acc. to picture.
When using a crane (E) or a similar
lifting mechanism, proceed following-
ly : - prepare 4 lifting belts (H) of suf-
ficient lifting capacity or endlesly
connected steal ropes of minimal
length 4 m,
- bend belts onto crane(of needy lift-
ing capacity) hook(J) and under
machine stand,
- use fillers and rope braces so that
ropes would not damage plastic parts
and the sliding table CV3,
- check up the stability of machine
hang at a moderate lifting up
eventually change the placing of
fillers and of rope braces,
- lift the machine carefully and slowly
and then relocate it without sudden
moving changings to chosen place.
Weight : PF 400 S ….. kg
Содержание PF 400 S
Страница 1: ...DIMENSION SAW PF 400 S Service instructions updated 9 2002 ...
Страница 17: ...6 3 Installment of demountable parts ...
Страница 35: ......