3.4
Installation premises
R
TAU N
steel boilers must be installed in a dedicated boiler
room, with adequately sized vents, in compliance with applica-
ble laws and standards.
If at all possible, the boiler should be installed on a raised base
to stop the burner fan sucking up dust and to facilitate installa-
tion of a condensate drain system.
The boiler condensate drain must be located above the height of
the lid of the system’s condensate neutraliser.
The gas supply pipe must be installed in such away that the
boiler’s panelling can be removed and the front door opened
without having to remove the burner.
9
In Belgium, boilers must be installed according to standards
NBN D51.003, NBN D30.003, NBN B61.002 (heat output < 70
kW), and NBN B61.001 (heat output >70 kW).
9
When installing the boiler, allow sufficient space around it
to access all safety and control devices and to permit easy
maintenance.
9
If the specific weight of the gas supply to the burner is
greater than the specific weight of air, install all electrical
parts at least 500 mm above floor level.
0
Do not install the boiler outdoors. It is not designed to work
outdoors and is not fitted with the necessary automatic an-
ti-frost systems to do so.
≥
1 m
≥
L
H1
≥
1 m
B
≥
1 m
L
~ 0,1 m
DESCRIPTION
TAU N
115
150
210
270
350
450
600
800
1000
1150
1250 1450
B - Width
750
750
750
850
850
900
900
1000 1000
1200
1200
1250
mm
L - Length
1350
1350
1350
1620
1820
1930
2140 2400 2700 2920 2920 3100
mm
H1 - Overall height ( base)
1420
1420
1420
1540
1540
1700
1700
2010
2010
2130
2130
2280