Installation instructions for qualified personnel

Important notes prior to 
installation

■ 

Observe the Operating 
Manuals for the indoor unit and 
the chiller or heating system or 
the heat pump system when 
installing the entire system.

■ 

The indoor units and water 
chillers and heat pump 
system work independently. 
A connecting line between the 
two is not necessary. 

■ 

Transport the unit in its original 
packaging as close as possible 
to the installation location. 
You avoid transport damage by 
doing so.

■ 

Check the contents of the 
packaging for completeness 
and check the unit for visible 
transport damage. 
Report any damage 
immediately to your contractual 
partner and the shipping 
company.

■ 

Select an installation location 
which allows air to flow freely 
through the inlet and outlet. 
(See section "Minimum 
clearances").

■ 

Do not install the unit in the 
immediate vicinity of devices 
which generate intensive 
radiation of heat or cold. 
Installation in the vicinity of 
heat or cold radiation reduces 
the unit output.

■ 

Lift the unit at the corners 
and not by the medium or 
condensate connections.

■ 

The medium connection lines, 
valves and connections must 
have vapour density insulation. 
If necessary, also insulate the 
condensate drainage line. 
In dual systems with cooling 
and heating modes, the 
requirements of the current 
Energy Savings Ordinance 
(EnEV) must be followed.

■ 

Seal off open lines to prevent 
dirt getting in and never kink or 
crimp the lines.

■ 

Avoid unnecessary bends. 
This minimises the pressure loss 
in the lines.

■ 

Make all electrical connections 
in accordance with applicable 
DIN and VDE standards.

■ 

Always ensure the electrical 
cables are properly connected 
to the terminals. Otherwise 
there is a risk of fire.

■ 

Adequate clearance must be 
provided to allow maintenance 
access to the control box and 
the valve assembly.

■ 

Only install the valve assembly 
or other attachments once the 
indoor unit has been installed.

Selecting the installation 
location 

Wall / ceiling unit KWK -4R

The indoor unit is designed for 
vertical wall installation, for 
instance underneath windows.  
However, it can also be used in 
the upper wall area (max. 1.25 m 
above floor level).

The unit is also designed for 
horizontal ceiling installation. In 
this case particular attention must 
be paid to the condensate drainage 
(see the Chapter "Condensate 
drainage connection").

Connection variants

The following connection variants 
can be used for the medium and 
condensate pipes and the control 
lines.

Installation material 

 

The indoor unit is attached using 
4 bolts to be provided by the 
customer.

Connection variants

3

1

4

2

1 Outflow through the wall on the left 

2 Outflow through the wall on the right 

3 Outflow through the floor on the left 

4 Outflow through the floor on the right

Minimum clearances

Observe the minimum clearances 
to allow access for maintenance 
and repair work in the suspended 
ceiling and to facilitate optimum 
air distribution for the cover.

Minimum clearances

KWK 100-4R to 400-4R
Wall installation with ground clearance

KWK 100-4R to 400-4R
Ceiling installation with air inlet plinth

1,000

1,000

300

300

Min. 100

1,000

1,000

300

0

300

REMKO KWK -4R

10

Содержание KWK 100-4R

Страница 1: ...KWK 100 4R KWK 150 4R KWK 250 4R KWK 400 4R Wall and ceiling chilled hot water units for heat pump systems Operation Technology Spare parts Edition GB F01 REMKO KWK 4R...

Страница 2: ......

Страница 3: ...or misprints Safety notes 4 Environmental protection and recycling 4 Transportation and packaging 4 Guarantee 5 Unit description 5 System layout 6 Operation 6 7 Shutdown 7 Care and maintenance 7 8 Tro...

Страница 4: ...it and its components must be set up connected and operated in accordance with the use and operating conditions stipulated in this manual and comply with all applicable local regulations Mobile units...

Страница 5: ...is designed for use indoors in the lower wall area vertical installation and for ceiling installation horizontal installation Operation is either individually or in groups using a room temperature co...

Страница 6: ...r warm water generator which extracts heat from the medium or heats the medium in a heat exchanger The cooled heated operating medium is then fed once again to the unit in the medium circuit Room temp...

Страница 7: ...nance work may only be carried out if the unit is disconnected from electrical power CAUTION Care Ensure the unit is protected against dirt mould and other deposits Clean the unit using a damp cloth D...

Страница 8: ...Switch the power supply and the unit back on Cleaning the condensate pump accessory The indoor unit may contain an integrated or separate condensate pump which pumps any accumulated condensate into ou...

Страница 9: ...r wait for time period to pass Filter is dirty air inlet outlet opening is blocked by debris Have the filters been cleaned Clean filters Windows and doors open Heating cooling output has increased Hav...

Страница 10: ...minimises the pressure loss in the lines Make all electrical connections in accordance with applicable DIN and VDE standards Always ensure the electrical cables are properly connected to the terminals...

Страница 11: ...the heat exchanger slide into the retainer keep the same air duct and after installing the heat exchanger remove the film and screw the unit back together in reverse order 5 Removing the heat exchang...

Страница 12: ...drainage line to the unit as described below Installation NOTE Installation should only be performed by authorised specialists Selecting the hydraulic connection 2 conductor cooling system Wall insta...

Страница 13: ...ow rate adjusted using hydronic balancing valves Additional automatic bleed valves must be provided in the supply and return flows at the installation s highest point The medium piping must not exert...

Страница 14: ...hich is not used must be permanently sealed a cap or similar CAUTION Condensate drainage connection Condensate drainage connection Condensate drainage connection Vertical mounting Horizontal mounting...

Страница 15: ...ed KWK 100 4R to 400 4R Neutral conductor Phase conductor Earth conductor Power supply 230V 1 50Hz Level 2 Level 1 Level 3 Condensate pump If the condensate which forms is to be removed by a condensat...

Страница 16: ...re and record all the required values in the commissioning report and check the safety functions 5 Check the unit control system using the functions described in the Chapter Operation Final tasks Reas...

Страница 17: ...ned heat exchanger 4 rows of tubes 1111746 1111747 1111748 1111749 3 Outlet grill 1111764 1111764 1111764 1111764 4 Control panel right 1111765 1111765 1111765 1111765 5 Control panel left 1111766 111...

Страница 18: ...6 5 26 5 27 5 36 5 25 5 26 5 34 5 Sound power level per stage dB A 34 37 43 34 41 45 35 36 45 34 35 43 Power supply V Hz 230 1 50 Enclosure class IP X0 Electr rated power consumption 1 kW 0 04 0 03 0...

Страница 19: ...ssure power Level V l h dB A dB A QH kW LA C V l h QH kW LA C V l h QH kW LA C V l h QH kW LA C V l h KWK 100 4R min 128 25 5 34 0 48 31 83 0 69 35 9 119 9 0 91 41 1 159 3 1 13 46 196 8 5 147 28 5 37...

Страница 20: ...in the field are more than just sales people above all they must be advisers to our customers in air conditioning and heating technology Customer service Our units operate precisely and reliably Howe...

Отзывы: