background image

    Level the hub by adjusting the leveling feet and 

check against the spirit level on the top of the 
Central Hub. 

    Repeat step 4 for each of the Leveling Feet.

    Insert the first Leg Assembly into the Central Hub. 

    Repeat steps 1 - 2 for the second Leg Assembly, 

securing the Leg Assembly to the Central Hub. 

2

    Insert the clevis pins on both sections and secure 

them into position with the R-clips provided.  

    Insert the Davit into the Central Hub for use.

Note: Please refer to the Assembly & Operation 
Guide of the applicable Davit system when used in 
conjunction with the PORTA BASE. 

21

PORTA

BASE

Assembling the PORTA BASE  [H Base]

Choose a suitable adjustment hole for the intended Davit.

Ensure all Leveling Feet are in contact with the surface so that 

the load is evenly distributed.

Leveling the H Base

Ensure both Leg Assemblies are secured using the same 

adjustment hole. 

The PORTA BASE [H Base] and its constituent components are described in the image below.

The H Base system will be delivered in three components which are the Left Leg Assembly, Right Leg Assembly and Central Hub. 

Appropriate PPE should be worn:      

  

Gloves      

  Protective Footwear      

  Hard Hat

Assembly Instructions

Left Leg Assembly

Right Leg Assembly

Leveling Feet

Central Hub

Leveling Feet

Leveling Feet

4

5

6

1

3

Содержание PORTA-BASE

Страница 1: ...US REIDLIFTING COM PORTABASE Assembly Operation Guide...

Страница 2: ...instructions and guidance notes carefully before using or operating the system They contain important information about how to handle and use the system in a safe and efficient way avoiding danger red...

Страница 3: ...ment to be used for lifting of materials and as a component of a PFAS Some employers may also prefer to keep such equipment distinctly separate If this is the case we would recommend that the equipmen...

Страница 4: ...any adverse weather conditions such as strong or gusty winds which could impose additional horizontal loads and affect the stability of the structure Stop using if weather is impacting on lifting and...

Страница 5: ...removed from service The substrate of the structure on which the product is placed must be able to sustain the loads specified for the device in all orientations permitted including a safety factor o...

Страница 6: ...ndicative F Maximum Rated Force Set up is indicative PFAS INFORMATION T DAVIT Type W Davit Radius Anchor Point A Anchor Point B Anchor Point C Anchor Point D Porta Base Fixed Socket 31 800 mm 22 2 kN...

Страница 7: ...NFORMATION PORTA DAVIT QUANTUM Reduced Radius PDQRW Davit Radius Anchor Point A Anchor Point B Anchor Point C Anchor Point D 31 800 mm 16 kN 3600lb 16 kN 3600lb 16 kN 3600lb 22 2 kN 5000lb This produc...

Страница 8: ...ORTA DAVIT QUANTUM 2 Winched PDQ2W Pin Position Davit Radius Anchor Point A Anchor Point B Anchor Point C Anchor Point D P1 51 1300 mm 12 kN 2600lb 12 kN 2600lb 12 kN 2600lb 22 2 kN 5000lb P2 55 1400...

Страница 9: ...formation is based on REID Lifting s recommendations and does not remove the responsibility of the user to comply with the relevant regulations and standards that are valid in the respective countries...

Страница 10: ...rown down and always placed carefully onto the ground Static Electricity For Zone 2 applications there is a potential risk of static electricity build up leading to an incentive spark To mitigate the...

Страница 11: ...sed in conjunction with the PORTA BASE 21 PORTABASE Assembling the PORTA BASE H Base Choose a suitable adjustment hole for the intended Davit Ensure all Leveling Feet are in contact with the surface s...

Страница 12: ...the Central Hub 23 PORTABASE Assembling the PORTA BASE Counterbalance Basket Assembly Choose a suitable adjustment hole for the intended Davit Ensure both Leg Assemblies are secured using the same ad...

Страница 13: ...the first side plate from the storage position at the bottom of the basket Insert the first side plate between the end plate channels Ensure the side plate sits correctly over the pin Secure in place...

Страница 14: ...asket always have the height adjustment legs fully retracted as shown in figure 2 Position the system in place for the lift before setting the height Manually raise each leg in turn and set the height...

Страница 15: ...29 PORTABASE PORTABASE Counterbalance 107 Max 91 Min 95 37 76 9 5 12 25 23 3 Height Adjustment Dimensions 13 17 45 63 72 Max 56 Min 4 Height Adjustment PORTABASE H Base...

Страница 16: ...subpart M The Lifting Operations and Lifting Equipment Regulations 1998 S I 1998 No 2307 The Provision and Use of Work Equipment Regulations 1998 S I 1998 No 2306 Machinery Directive 2006 42 EC PPE Re...

Страница 17: ...detent pin and fully engage before loading the system Insert the clevis pin and secure with the clip before loading the system Restraint point only Read the operational manuals before using the system...

Страница 18: ...The ATEX rating of the product if applicable CE Marking Minimum breaking strength MBS for ANSI Z359 18 Insert data from serial numbers found on product into table here Product labelling The following...

Страница 19: ...Date Inspected by Pass Fail Corrective Action Comments Periodic Examination Repair History 37 PORTADAVIT QUANTUM Notes Notes...

Страница 20: ...Notes Notes...

Страница 21: ...Ltd All company and product names are Trade Mark and Trade Name protected and all REID Lifting Ltd Product IPR is protected under Patents Patents Pending and or Design Rights Contact Us REID Lifting I...

Отзывы: