CHECKLIST AFTER INSTALLATION
The MOSAIC system is able to detect the faults that occurs in each own
module.
Anyway to have the system perfect operation perform the following checks
at start up and at least every one year:
OPERATION / CONTROL
COMPLETE
1.
Verify the correct fixing of MOSAIC to the Omega rail
❒
2.
Operate a complete system TEST
(see "TESTING the system", in the Mosaic instruction manual
available on the ReeR website)
❒
3.
Verify that all the cables are correctly inserted and the terminal
blocks well screwed
❒
4.
Verify that all the leds (indicators) light on correctly
❒
5.
Verify the positioning of all the sensors connected to MOSAIC
❒
6.
Verify that all the external indicators (lamps) work properly
❒