Fig 2.0 Example Setup Plan Setup 1

Description

Value

Comment

Configuration (Single or Twin)

18 ft (5.5 m)

Left Side

Platform Length (6.5 ft or other)

24 ft

Mast Distance from Structure

6 in

Shared Mast Setup?

Yes

Left Side

Work Height

100

Masts [Height (ft) / 4.8] (2x for Twin)

100/4.8 = 20.8 (2x) = 42

Minimum Ties Needed [Ht (ft) / 18 + 1] 100/18+1 = 6.6 => 7 (2x) = 14

14

Climbing Unit

2

Platform Support

2

Base

2

Drill

2

Extension Cords

3

100 ft

Power Strip / Splitter

2

LAYOUT PLANNING

2

Содержание PowerMast Series

Страница 1: ...Operator s Safety Manual www reechcraft com powermast P N 4026288...

Страница 2: ...Craft Inc product is patented and protected in the United States US Patent 6981573 All other US and International Patents Pending Using this product in methods not indented by ReechCraft Inc are stric...

Страница 3: ...upport Assembly 11 Tie Assembly 12 Specifications 13 SECTION 2 LAYOUT PLANNING Layout Plan 23 Ground Preparation 25 Tie Planning 25 SECTION 3 ERECTINGTHE SYSTEM Pre Assembly 26 Erect Base Unit 28 Asse...

Страница 4: ...e the Warranty Period The End User Warranty is non transferable by the End User and only applies to Product manufactured after September 1 2018 During the Warranty Period Reechcraft warrants Products...

Страница 5: ...uties taxes or environmental fees including but not limited to the disposal or handling of materials Parts purchased or sourced by suppliers other than Reechcraft or a Reechcraft Reseller are not cove...

Страница 6: ...End User Warranty and any such unenforceability in that jurisdiction shall not make that provision unenforceable in any other jurisdiction SAFETY GUIDELINES 1 Safety comes first To help ensure safety...

Страница 7: ...ep a telephone list of emergency numbers 12 Never overload the system beyond the duty rating of 750 lbs 340 kg Refer to the loading section of the user manual for more information Although the system...

Страница 8: ...by ReechCraft 8 Section SYSTEM CONFIGURATIONS Fig 1 0Tied Configuration Single Mast Twin Mast Fig 1 1a Free Standing Configuration Single Mast Twin Mast GENERAL SYSTEM INFORMATION 1...

Страница 9: ...888 600 6160 9 Section GENERAL SYSTEM INFORMATION Drill Bracket with Adjustable Lock Collar Drop Stop Lock Pawl Platform Support Latch Pins Platform Front Hold Down Overspeed Brake Gearbox 3 8 Nut Dr...

Страница 10: ...by ReechCraft 10 Section GENERAL SYSTEM INFORMATION 5 ft Mast Section Base MAST AND BASE ASSEMBLY Fig 1 3 Base Foot Pad 1...

Страница 11: ...reechcraft com PowerMast 888 600 6160 11 Section MAST AND BASE ASSEMBLY Fig 1 4 Free Standing Base PLATFORM SUPPORT ASSEMBLY Fig 1 5 GENERAL SYSTEM INFORMATION Platform Support Rear Hold Down Bracket...

Страница 12: ...by ReechCraft 12 Section TIE ASSEMBLY Fig 1 6 Fig 1 7 Tri MastTie GENERAL SYSTEM INFORMATION Tie Mount Adjustable Bracket Mast Connector Weld Arm Extension Tube 1...

Страница 13: ...Pawl Overload Clutch Overspeed Brake Emergency Lowering Manual Hand Crank Available Mast ConnectionType Interference Locking Cam Drive System 120 1 Clutch ProtectedTransmission Required Voltage 110 V...

Страница 14: ...6 5 in 152 419 mm H Maximum Platform Height Tied 194 ft 59 1 m Free Standing Indoor 46 2 ft 14 1 m Free Standing Outdoor 26 8 ft 8 2 m I Maximum Platform Height Above LowerTie During Use Single MastTi...

Страница 15: ...www reechcraft com PowerMast 888 600 6160 15 Section GENERAL SYSTEM INFORMATION D F B B A C H K I J E Specifications Tied Configuration Fig 1 10 1...

Страница 16: ...rigger Width Standard 75 in 1905 mm D Outrigger Depth Standard 101 in 2565 mm E Platform Clearance Mast Side Standard 49 7 in 1262 mm F Platform Clearance Gearbox Side Standard Retracted 25 in 635 mm...

Страница 17: ...www reechcraft com PowerMast 888 600 6160 17 Section Specifications Free Standing Configuration Fig 1 12 www reechcraft com PowerMast 888 600 6160 17 Section 1 GENERAL SYSTEM INFORMATION...

Страница 18: ...s rated load on each climbing unit 4 Mast Locations a What is the mast distance from the wall Will there be any special provisions for ground support needed 5 Tie Locations a 18 ft 5 5 m is MaximumTie...

Страница 19: ...m Left Side Platform Length 6 5 ft or other 24 ft Mast Distance from Structure 6 in Shared Mast Setup Yes Left Side Work Height 100 Masts Height ft 4 8 2x forTwin 100 4 8 20 8 2x 42 MinimumTies Needed...

Страница 20: ...or 841 lbs 7 lbs ft x 200 2241 lbs 1016 kg Surface Area of Base Plate 93 sq in 600 sq cm Maximum Ground Pressure on Base 200 ft 750 lbs Load 24 psi 1 69 kg sq cm Note Actual system weight is less for...

Страница 21: ...tally on the ground track up and slide on the climbing unit gearbox up engaging the gearbox drive gear to the mast track 2 Use the drill to extend the mast through bottom rollers PRE ASSEMBLY Fig 3 0...

Страница 22: ...ion 3 ERECTING THE SYSTEM 3 Secure the base to the bottom of the mast PRE ASSEMBLY CONT D Fig 3 2 Fig 3 3 1 Align track and place together 3 Rotate Cam Lock Lever both sides 2 Rotate Cam Lock Lever 2...

Страница 23: ...ermine the complete list of equipment required for erection Be sure all components have been inspected and maintained in accordance with product labels on the unit and information contained in this ma...

Страница 24: ...Move mast to desired position and tighten extension tube bolts 7 Fully secure every bolt connection on tie before proceeding ERECT BASE UNIT CONT D Fig 3 5 AnchorTie to Wall While anchoring tie arms s...

Страница 25: ...aft com PowerMast 888 600 6160 25 Section 8 Anchor points are available on the base ERECT BASE UNIT CONT D 9 Rotate pins up and remove ASSEMBLE PLATFORM SUPPORT Fig 3 6 Fig 3 7 Anchor here 3 Erecting...

Страница 26: ...eechCraft 26 Section 10 Measure platform bottom to midrail top Position support so top rail is just below gearbox ASSEMBLE PLATFORM SUPPORT CONT D Fig 3 8 Midrail Top Platform Bottom 3 ERECTING THE SY...

Страница 27: ...www reechcraft com PowerMast 888 600 6160 27 Section 11 Attach platform to platform support s ATTACH PLATFORM Fig 3 9 Fig 3 10 3 Erecting the system...

Страница 28: ...r climbing unit to allow for a temporary 10 degree angle for emergency one operator descent Be sure the platform only moves slightly side to side but does not lift off the platform support in a way th...

Страница 29: ...160 29 Section 13 Add masts by raising the platform approximately 3 in 7 5 cm below top of the mast Connect the masts Fig 3 12 ADDING HEIGHT Fig 3 12 Note Refer to Section 4 for Power System Installat...

Страница 30: ...by ReechCraft 30 Section 14 Fasten tie to mast in platform before stacking Fig 3 13 15 Stack masts and raise up to untied ties Fig 3 14 ADDING HEIGHT CONT D Fig 3 13 Fig 3 14 3 ERECTING THE SYSTEM...

Страница 31: ...ase platform rigidity ADDING HEIGHT CONT D Important For a Single MastTied configuration you shall not do work above a tie For aTwin MastTied configuration it is allowable to work while the platform i...

Страница 32: ...maximum platform height of 194 ft 59 1 m or working height of 200 ft 61 m Where possible it is preferred to stagger ties to increase platform rigidity Fig 3 16 ADDING HEIGHT CONT D Fig 3 16 200 ft 61...

Страница 33: ...ground Fig 1 14 Important This is the normal position the outriggers should be in to achieve the full ratings of the system Consult your dealer or ReechCraft customer service for information on altern...

Страница 34: ...about 10 feet above the base Subsequent ties will be secured every 10 feet or less Fig 1 15 Important DO NOT elevate more than 5 feet above the tie directly below the platform Important Ties must be s...

Страница 35: ...and make sure the locking flange is fully engaged into the mast channel See figure 1 17 Fig 1 16 Proper Flange Orientation Fig 1 17 Important Locking flange MUST be fully secured into the mast channel...

Страница 36: ...vertical during the assembly process 2 Securing theTie Finish the tie installation by securing the twist lock flanges on the front mast Note It is recommended to use a bar clamp or ratchet strap to pu...

Страница 37: ...tower installation Finish Erecting theTower Finish the tie installation by securing the twist lock flanges on the front mast Note It is recommended to use a bar clamp or ratchet strap to pull the mid...

Страница 38: ...our local dealer Refer to Fig 4 0 for drill and electrical cord requirements 4 Assemble the supplied 3 8 in 9 5 mm driver to the drill Important Only use the driver supplied with the system or equival...

Страница 39: ...racket and on to the input shaft Remove any obstructions and make necessary adjustments so the drill can be inserted freely 8 The drill bracket is designed to hold the drill on the gearbox input shaft...

Страница 40: ...he platform system Fig 4 4 Eliminate any conditions which would allow the electrical cords to catch on clothing tools materials or any other obstruction POWER CORD INSTALLATION Fig 4 5 11 Ensure that...

Страница 41: ...can be connected into the power supply by way of an in line power board with circuit protected switch This configuration enables one lead to hang down to the ground circuit making cord management eas...

Страница 42: ...personnel in the way of operation 4 While lifting the platform always keep hands free from any moving parts Fig 5 0 Raise the platform by placing the drill in the forward clockwise position and pullin...

Страница 43: ...engaged into the track and will need to be released before going down Lift the system up slightly until lock lever is released then proceed with lowering Important While lowering the platform it is be...

Страница 44: ...s suited to be stored outdoors However storing the system indoors is advised to maximize the life span of your investment Keep the system component inventory organized and labeled with a physical reco...

Страница 45: ...www reechcraft com PowerMast 888 600 6160 45 Section 6 TRANSPORT STORAGE AND MAINTENANCE inspection and Maintenance Logs...

Страница 46: ...ReechCraft 46 Section TRANSPORT STORAGE AND MAINTENANCE 6 DAILY INSPECTION AND MAINTENANCE LOG 1 OF 2 Competent Person Print Date of Inspection Company Name Jobsite Signature of Competent Person Comme...

Страница 47: ...Be sure the drill assembly with nut driver freely moves on to hex input shaft of the gearbox and engages fully Secure the drill to the drill bracket by tightening the wing nut Platform Support Inspect...

Страница 48: ...eechCraft 48 Section TRANSPORT STORAGE AND MAINTENANCE 6 WEEKLY INSPECTION AND MAINTENANCE LOG 1 OF 2 Competent Person Print Date of Inspection Company Name Jobsite Signature of Competent Person Comme...

Страница 49: ...beside the climbing unit lower the climbing unit allowing the lock lever to fully engage the track and clutch out the gearbox for 3 seconds When functioning properly the drill bracket will place a sm...

Страница 50: ...eechCraft 50 Section TRANSPORT STORAGE AND MAINTENANCE 6 ANNUAL INSPECTION AND MAINTENANCE LOG 1 OF 2 Competent Person Print Date of Inspection Company Name Jobsite Signature of Competent Person Comme...

Страница 51: ...embly with climbing unit next to a structure Taking all necessary safety precautions and with the climbing unit less than 0 5 m off the ground load 1000 lbs and secure to the unit no work platforms et...

Страница 52: ...Reechcraft Inc 845 34th St S Fargo ND 58102 888 600 6160 www reechcraft com PowerMast...

Отзывы: