4-INSTALLATION AND ASSEMBLY
PREPARATION AND UNPACKING
The Performa is delivered complete with all its electrical, mechanical and hydraulic components (excluding the circulator
kit -OPTIONAL) and having been tested in the factory.
The boiler is delivered in a single package and the packaging of the selected hydraulic kit - optional accessory is added after.
Remove the cardboard, remove the S-brackets that secure the boiler to the pallet as well as the “x” and “y” screws. There are two S-fixing
brackets, one at the front and one at the back.
Install the boiler in the area set aside for it, making sure it conforms to the
requirements. The boiler body or unit must always be kept in a vertical position
when moved, and only ever moved using suitable lifting trolleys.
The packaging materials are neither toxic nor harmful, and therefore no
particular disposal measures are required.
After removing all the packaging, check that the boiler is complete and not
damaged. If in doubt, contact the retailer.
FIGURE 1 - PACKAGING
FIGURE 2 - REMOVING THE PACKAGE BRACKETS