background image

Weekly

For low-pressure boilers, test low-water cut-off device. 

(With boiler in pre-purge, depress the low water cut-

off test button.  Boiler should shut-off and ignition fault 

light should come on. Depress reset button on front of 

boiler control panel to reset).

Monthly

1.  Check flue, vent, stack, or outlet dampers.

2.  Test blower air pressure. (See the I&O Manual.) 

Replace the filter when the intake air pressure 

increases by –0.5 in. WC from the reading record-

ed on the start-up checklist.

3.  Test high and low gas pressure interlocks (if 

equipped). (See “Safety Inspection” in the I&O 

Manual.)

Semi-Annually

1.  Recalibrate all indicating and recording gauges.

2.  Check flame failure detection system components. 

3.  Check firing rate control by checking the mani-

fold pressure. (See “Manifold Check” in the I&O 

Manual.)

4.  Check piping and wiring of all interlocks and shut-

off valves.

5.  Check air filter and replace as necessary.

Annually

1.  Test flame failure detection system and pilot turn-

down. 

2.  Test high limit and operating temperature. (See 

“Post Start-Up Check” in the I&O Manual.)

3.  Check flame sensor.

4.  Conduct a combustion test at high and low fire. 

Carbon dioxide should be 8.6 to 9.4% at full fire 

for natural gas, and between 9.9 to 10.7% for pro-

pane gas. Carbon monoxide should be <100 ppm.

5.  Check valve coil for 60 cycle hum or buzz. Check 

for leaks at all valve fittings using a soapy water 

solution (while boiler is operating). Test other oper-

ating parts of all safety shut-off and control valves 

and increase or decrease settings (depending on 

the type of control) until the safety circuit opens. 

Reset to original setting after each device is test-

ed.

6.  Perform leakage test on gas valves (See I&O 

Manual). 

7.  Inspect and clean burner using shop air (See I&O 

Manual).

As Required

1.  Recondition or replace low water cut-off device.

2.  Check drip leg and gas strainers.

3.  Check flame failure detection system. (See “Post 

Start-Up Check” in the I&O Manual.) Verify high 

and low fire flame signal, compare to start-up data,

4.  Check flame signal strength as noted on display.

5.  Check igniter (Resistance reading should be 

40-75 ohms at 77°F (25°C).

6.  Check firing control by checking manifold pres-

sure. (See “Manifold Check” on I&O Manual).

7.  Test safety/safety relief valves in accordance with 

ASME Heater and Pressure Vessel Code Section 

IV.

8.  Inspect filter and replace as necessary.

Содержание XVers 856-3006

Страница 1: ...e or explosion may result causing property damage personal injury or loss of life QUE FAIRE SI VOUS SENTEZ UNE ODEUR DE GAZ Ne pas tenter d allumer d appareils Ne touchez à aucun interrupteur Ne pas vous servir des téléphones dansle bâtiment où vous vous trouvez Appelez immédiatement votre fournisseur de gaz depuis un voisin Suivez les instructions du fournisseur Si vous ne pouvez rejoindre le fou...

Страница 2: ...r water A AWARNING To minimize the possibility of improper operation serious personal injury fire or damage to the heater Always keep the area around the heater free of combustible materials gasoline and other flammable liquids and vapors Heater should never be covered or have any blockage to the flow of fresh air to the heater CAUTION This boiler requires forced water circulation when the burner ...

Страница 3: ......

Страница 4: ...E MISE EN MARCHE 1 ARRÊTEZ Lisez les instructions de sécurité sur la portion supérieure de cette étiquette 2 Réglez le thermostat à la température la plus basse 3 Coupez l alimentation électrique de l appareil 4 Cet appareil ne comporte pas de veilleuse Il est muni d un dispositif d allumage qui allume automa tique ment le brûleur Ne tentez pas d allumer le brûleur manuellement 5 Enlever le pannea...

Страница 5: ...NT OF HEATER GAS VALVE GAS TRAIN HEAT EXCHANGER T P GAUGE FLOW SWITCH GAS SUPPLY CONNECTION WATER OUTLET 3 FLANGE FLOW SENSOR WATER INLET 3 FLANGE OPTIONAL LOW GAS PRESSURE SWITCH VENT TEMP SENSOR LOW WATER PROBE HIGH GAS PRESSURE SWITCH OPTIONAL ON MODELS 0856 2506 GAS SHUTTER PIM HIGH VOLTAGE SWITCH VERSA BOARD 3 POSITION LOW VOLTAGE SWITCH TOUCHSCREEN DISPLAY LOW VOLTAGE FIELD CONNECTION AIR FI...

Страница 6: ...ing procedures are recommended and are good practice for all XVers installations Daily 1 Check gauges monitors and indicators 2 Check instrument and equipment settings See Post Start Up Check in the I O Manual MAINTENANCE Suggested Minimum Maintenance Schedule Regular service by a qualified service agency and maintenance must be performed to ensure maximum operating efficiency Maintenance as outli...

Страница 7: ...me sensor 4 Conduct a combustion test at high and low fire Carbon dioxide should be 8 6 to 9 4 at full fire for natural gas and between 9 9 to 10 7 for pro pane gas Carbon monoxide should be 100 ppm 5 Check valve coil for 60 cycle hum or buzz Check for leaks at all valve fittings using a soapy water solution while boiler is operating Test other oper ating parts of all safety shut off and control v...

Страница 8: ...www raypak com Raypak Inc 2151 Eastman Avenue Oxnard CA 93030 805 278 5300 Fax 805 278 5468 Litho in U S A ...

Отзывы: