24
Figure 10 The main interface is displayed when the communication connection is normal
4.5
Steps of Installation
a)
Carefully takeout the laser from the box and move it to the installing position and then lock
the casters;
b)
Remove the output cable protective cap and check the output lens for dust with strong light
and clean it if necessary, then cover the output cable protective cap;
c)
Install the output cable on the processing equipment according to the actual situation
(install the output head cooling water pipe at the same time), pay attention to the output
cable and head,then remove the protective cap andconfirm that the output lens is clean and
install the output head
;
d)
Connect cooling water pipe;
e)
Connect the control line and power according to the control mode.
4.6
Steps of Starting
All electrical connections must be finished before the laser is powered on;
Make sure the air switch is OFF and the emergency stop button (EMERGENCE STOP) on
the front panel of the laser has been pressed down.