Before leaving the site, check the operation of the
programmer and the control thermostat are working
correctly and are capable of controlling the burners
correctly. Check the operation of both control boxes.
In the event of a flame failure, the control boxes should
cut off the oil supply by closing the solenoid valves. The
reset buttons will then be illuminated.
WAIT 1 MINUTE BEFORE RESETTING THE
CONTROL.
Check that:-
1.
The boiler system is full of water and all the valves
are fully open.
2.
The programmer is set to continuous heating.
3.
Ensure that the electricity supply is ON, that the pump
is running and the boiler thermostat is ON.
The boiler and pump should run until the system is hot
and an inspection is made for water leaks.
The system should then be turned off and rapidly drained
whilst still hot, with all manual and automatic valves in the
open position. The system should then again be filled and
cleared of any air locks. Whilst refilling the system it is
essential that a corrosion inhibitor is added to the feed
water.
When all air locks have been removed and the system is
hot the by-pass should be adjusted to ensure a quiet
operation and the radiators balanced.
4.
Allow the pump adjuster to maintain a “flow and return”
differential temperature of 10° - 14°C.
Checks must be made by the installer to see that the
differential is obtained after the boiler ‘Flow’ temperature
is stabilised.
The system should be balanced by regulating the water
flow rate through individual heat emitters to ensure
satisfactory water temperature at each emitter.
5.
When the water system reaches working temperature
check that the boiler thermostat operates.
1.
Advise the User of the precautions to prevent damage
to the heating system and to the building in the event
of the heating system being inoperative during frost
conditions.
2.
Advise the User that, for continued efficient and safe
operation of the appliance, it is important that
adequate servicing is carried out at regular 12 monthly
intervals.
3.
Hand the Operating Instructions to the User and
demonstrate the correct operation of the appliance
and system controls.
4.
Leave the Installation and Servicing Instructions with
the User.
26
Commissioning Instructions
ANCILLARY CONTROLS CHECK
INSTRUCT THE USER
BOILER CONTROL CHECK
Содержание 660
Страница 16: ...16 Site requirements Fig 6 680KCD C F 780KCD C F Rayburn 600 700 Wiring 111MB for independent Satronic boxes ...
Страница 19: ...Installation requirements 19 Fig 12 ALL BAFFLES MUST BE STACKED IN PLACE AS DIAGRAM ABOVE DESN 515919 ...
Страница 32: ...31 ...
Страница 33: ...33 ...
Страница 34: ...34 ...
Страница 35: ...35 ...