E. Finishing Material
It is important that the finishing material is determined before
the appliance is secured to the floor. Depending on the fin
-
ishing material and installation method, the appliance may
need to be positioned further in or out of the wall.
There are three ways finishing material can be applied:.
1. Behind the mounting frame
. Flush with the mounting frame
. Proud of the mounting frame
1. Behind the Mounting Frame
The mounting frame is designed to have a 1/ inch (1mm)
overlap on the sides and the top of the framing opening.
Figure 28.1.
NOTICE:
Non-combustible material is not needed to finish
this appliance.
Positioning the nailing flanges:
• Slide the nailing flanges all the way to the front and this
will set the appliance for 1/ inch (1mm) sheet rock.
• If tile, marble or other flat surface finish material is desi
-
ered and you want the mounting frame to cover the cut
edge, set the nailing flanges at a dimension of the sheet
rock thickness plus the finishing material thickness.
Figure 28.2.
Example: Sheetrock = 1/2 inch (13mm)
Finish Material = 3/8 inch (9.5mm)
Move flange: 7/8 inch (22mm)
2. Flush with the Mounting Fram
e
The finish material can not be thicker than 1-1/ inches
(8mm) to use this method.
Figure 28.3.
• Set the nailing flanges for sheet rock thickness and
install the appliance.
• Install the mounting frame.
• Install the finishing material to edge of the mounting
frame.
3. Proud of the Mounting Frame
This method is mainly used for a brick or stone installation.
When finishing material is proud of the mounting frame
and front, there must be a 1-1/4 inch (mm) airflow clear
-
ance in front of the mounting frame.
Figure 28.4.
Use the masonry spacer supplied with the Front to position
the finishing material at the proper dimension. Remember
to keep the Front opening clearances in mind when finishing
material is proud of the Front.
(See pages 29-30)
.
• Set the nailing flanges for sheet rock thickness and
install the appliance.
• Install the mounting frame.
• Install the finishing material to edge of the mounting
frame.
•
Complete the installation following all specified clear
-
ances to combustibles.
Figure 28.1.
Figure 28.2
Figure 28.3.
Figure 28.4.
Adjustable Nailing Flange
Adjustment Screw
Front of Fireplace
7/8 in
(22mm)
Mounting Frame
Finishing Material Behind
the Mounting Frame
Mounting Frame
Finishing Material Flush
with Mounting Frame
Door Frame
Finishing Material Proud of the Door Frame
Maintain 1-1/4 inch (32mm) air
clearance in front of door frame
Masonry Spacer