background image

46

47

 

Slowly open the valve by turning the spindle anti-clockwise 
until the required flow rate in l/min is achieved in the flow 
meter window.

When adjusting the manifold flow rates care should be taken 
to ensure that the adjustment spindle is not left with any of the 
thread showing.
In order to carry out any maintenance to the installation it is 
possible to isolate individual circuits by closing both the flow 
and return ports, as shown in the diagram below.

NOTE:

 The isolating valve fitted to the manifold flow meter 

is not used for balancing purposes.
If it becomes necessary to close off a manifold completely, 
this can be done by using a ¾” brass cap with a suitable rubber 
washer insert.
Once all of the circuit flow rates have been adjusted the 
system should be left to operate for a short period whilst any 
remaining air is removed. Once this has been done the flow 
rates should be re-checked and adjusted if necessary before the 
actuator heads are fitted. If the actuator heads are not likely 
to be fitted for a while then it is recommended that the blue 
caps are used in order to protect the flow rate settings and 
prevent any debris from entering the flow valve assembly.

IMPORTANT NOTE: 

When using the PB970014 Modulating 

Pump Unit to ensure that the primary boiler flow temperature 
provided at the manifold is at least 15°C hotter than the 
required manifold operating temperature. This is due to 
the fact that this manifold uses an ‘injector method’ to mix 
down the primary water. Furthermore, when balancing the 
system with this particular manifold kit please ensure that the 
modulating pump is set to a fixed head speed whilst making 
any adjustments.

SYSTEM COMMISSIONING

Initial system filling

Close the manifold isolating valves (1) & (2). Connect a hose pipe 
to the manifold return drain off point (4) and take to a drain. 
Connect a second hose to the manifold filling point (3) and attach 
to a mains cold water supply (3 bar max). The connections to 
the manifold drain and fill points are ¾” BSP. Use flexible ¾” 
tap connectors for the simplest method of connection.
Close all under floor heating circuits except one, by screwing 
down the blue caps and closing the isolating valves situated on 
top of the manifold flow meter. Flush the first circuit with mains 
cold water until all of the air has been purged. Once this has 
been done close the first circuit and repeat the process for all of 
the other circuits on the manifold.
Once the system has been filled and purged of air, and before 
any screed is laid, a system pressure test must be carried out to 
confirm the integrity of the installation. It is recommended that 
this test be done using a suitable hydraulic pressure test kit and 
not with air.

NOTE:

 The system pressure test should be carried out with the 

manifold pump pack removed.
Close the manifold isolating valves and connect the pressure 
test pump to the manifold flow rail using the ¾” threaded 
connection on the filling/drain-off point (3). Pressurise the 
system to 6 bar max and leave under pressure for 1 hour. 

Once the pressure test is complete reduce the system pressure 
down to 3 bar to protect the pipework whilst any screeding 
process is carried out.

IMPORTANT NOTE:

 Do not leave the system under pressure 

during periods of extreme cold weather or when there is a risk 
of freezing.

System balancing

Once the system is up and running it is necessary to balance the 
system in accordance with the design data provided. 
This should be done using the following method:
Ensure that the boiler and main system duty pump are operating 
correctly and that sufficient heat input and flow rates are being 
provided at the manifold(s).
Set the under floor heating controls to call for heat and 
check to see that the two-port zone valve and manifold pump 
are energised.

Remove the blue cap from the manifold flow port and, 
using the bleed key provided, turn the flow adjustment spindle 
clockwise to completely close the circuit.

Once installed, Polypipe under floor heating systems should be tested thoroughly 

to ensure they are working effectively, including initial filling of the system 

and system balancing. If you require any further information please contact 

the Polypipe Technical Team on 01709 770000.

1

2

4

3

Содержание Under Floor Heating Systems

Страница 1: ...s Broomhouse Lane Edlington Doncaster DN12 1ES Tel 01709 770 000 Fax 01709 770 001 2410 London Road Mount Vernon Glasgow G32 8XZ Tel 0141 778 8822 Fax 0141 778 2703 Dromore Road Lurgan Craigavon Co Ar...

Страница 2: ...revious printed copies will become out of date The latest version of our installation advice including a downloadable version of the current Technical Installation Guide can be found at our trade webs...

Страница 3: ...xtensive back up service Technical representation available to discuss systems in general and particular projects www ufch com Technical Installation CD Specialist Technical Hotline on 01709 770000 En...

Страница 4: ...he floor screed is required by Building Regulations Edge insulation also acts as an expansion joint Floating Floor When installed in floating floors Polyplumb pipe is simply pressed in to the pre form...

Страница 5: ...r requires a bespoke design You then simply input data for each room providing floor type room size and control zones to calculate the required pack All packs have a single order code and include all...

Страница 6: ...h when heated will reduce to 8 9 and cause only a very small amount of shrinkage The floor will re absorb some moisture when the heating is not operating and the moisture content will increase to 12 1...

Страница 7: ...d around the perimeter of the room using staples so as to prevent possible risk of the panels lifting Preparing the pipe Step 4 You will need to remove the coil from the bag leaving the shrink wrap on...

Страница 8: ...ted the screed cover can be applied Care should be taken to ensure that the screed is tightly compacted around the pipe to ensure that no voids are present The system should remain under pressure 6 ba...

Страница 9: ...nder pressure whilst the flooring is laid Finishing The room can then be finished by fitting 18mm or 22mm tongue and groove sheets of chipboard glued on the edge over the floating floor system Mark th...

Страница 10: ...hed downwards and away from the underside of the timber finished floor covering as this could lead to potential underperformance of the system Testing Step 4 Once the pipe circuits have been installed...

Страница 11: ...These can be fixed directly through the spreader plate down in to the joists below It is important to indicate the position of pipework in areas where the additional fixing of items such as carpet gri...

Страница 12: ...heir high output at relatively low flow temperatures Modular Heating Panels are ideal for maximising heat efficiency and lowering energy consumption In most installations it is not necessary to cover...

Страница 13: ...should be selected The span is defined as the free space from wall to wall that needs to remain uninterrupted by trimmers or other services Ideally install MHP panels prior to other services whenever...

Страница 14: ...omes into direct contact with it Always ensure that electrical cables are not in physical contact with the MHP panels using tape or a polythene strip Finishing Once you have connected your system up t...

Страница 15: ...for heavyweight floor coverings such as ceramics or where the floor covering needs to be secured directly to the panel e g solid wood Overlay Lite is a high compressive strength lightweight insulated...

Страница 16: ...is should be the first consideration for most projects The more structural nature of Overlay however makes it ideal for direct tiling or application of floor finishes which need to be fixed or screwed...

Страница 17: ...mple of blanking in a bathroom Example of squaring off an irregular room plan Room layouts The following diagrams show some examples of room shapes pipe requirements and interruptions pillars hearths...

Страница 18: ...wood floors they can be discretely screwed through the tongue and groove directly into the Overlay panel avoiding pipe circuitry to minimise movement in the floor covering If over boarding with 6mm p...

Страница 19: ...r covering as normal It is advisable to mark out pipe positioning to avoid stapling pipes when fitting carpets 36 37 Overlay Lite for lightweight floor coverings Installation Laying end returns Step 1...

Страница 20: ...stic hot water primary circuits To provide independent hydraulic control of the entire system it is important that the installation is designed as an S Plan or S Plan Plus configuration which allows f...

Страница 21: ...d in under floor heating systems is less than that required for radiators or stored hot water If these other services are connected to the same boiler it will be necessary to control the water tempera...

Страница 22: ...iring centre and slave units Available in two surface finishes and offers the following features Large touch screen display with high visibility blue LED backlight On screen display shows current stat...

Страница 23: ...distribution pipe work Connection from nearest radiator 260mm 200mm Pump Pipe thermostat Heating return Heating flow Under floor heating flow Under floor heating return Thermostatic blending valve Pu...

Страница 24: ...ible tap connectors for the simplest method of connection Close all under floor heating circuits except one by screwing down the blue caps and closing the isolating valves situated on top of the manif...

Страница 25: ...resistant to the build up of scale Short term chlorination for disinfection of supply pipe work and normal levels of chlorine in UK domestic water supplies will not have an adverse effect on the integ...

Страница 26: ...ng should be done with all switches on and room thermostats calling Fault finding complete Adjust pump speed and set flow rates in accordance with the system design data as provided NO NO Is the boile...

Страница 27: ...Manufacturing quality assurance In accordance with BS ES ISO 9001 2000 BSI registered firm Certificate FM00318 Installation standard To follow the recommendations of BS5955 Part 8 2001 Plastic Pipewo...

Страница 28: ...OR HEATING REQUIREMENTS Manifold Position s Please also indicate on drawing Floor Type Solid Suspended Floating MHP Overlay Overlay Lite Ground Floor 1st Floor 2nd Floor CONSTRUCTION DETAILS If NOT to...

Отзывы: