4
installation manual
Evaluate the ceiling construction and install using
Ø
10 hanging
screw bolts.
Keep indoor unit, outdoor unit, power supply wiring, and
transmission wiring at least 1 meter away from televisions and
radios. This is to prevent image interference and noise coming
from those electrical appliances. (Noise may be generated
depending on the conditions under which the electric wave is
generated, even if a 1 meter distance is kept.)
5.2 Install the Main Body
There is sufficient room for installation and maintenance.
The ceiling is horizontal, and its structure can endure the
weight of the indoor unit.
The outlet and the inlet are not impeded, and the
influence of external air is the least.
The air flow has reach throughout the room.
The connecting pipe and drainpipe can be easily
removed.
There is no direct radiation from heaters.
5. INDOOR UNIT INSTALLATION
5.1 Installation Location
(Refer to Fig. 5-1, Fig. 5-2, and Table 5-1 for specific details.)
The indoor unit should be installed in a location that meets
the following requirements:
4. INSPECTING AND HANDLING THE UNIT
On delivery, the package should be inspected, and any damage
should be reported to the service agent immediately.
When handling the unit, take into account the following:
- Fragile, handle the unit with care.
- Keep the unit upright, in order to avoid compressor
damage.
Pre-determine the path along which the unit is to be
brought in.
Move and carry this unit without changing its original
packaging position, by as much as possible.
When lifting the unit, always use protectors to prevent
belt damage, and pay special attention to the position of
1
2
3
4
CAUTION
Fig.5-1
≥35mm (1”-5/8)
≥1000mm
(40”)
≥ 35mm (1”-5/8)
≥ 35mm (1”-5/8)
Fig. 5-2
Please
Refer to Fig. 5-3
and
Fig. 5-4
for the hanging screw
bolts distance.
The handling of the ceiling varies with construction details,
consult the construction specialist for specific conditions.
Do keep the ceiling flat. Consolidate the roof beam to avoid
possible vibration.
1 Installing Ø10 hanging screw bolts. (4 bolts)
After selection of the installation location, position the refrigerant
pipes, drain pipes, indoor & outdoor wires to the connection
points before hanging up the machine.
Cut off the roof beam.
Strengthen the place that has been cut off, and consolidate
the roof beam.
Installation of hanging screw bolts:
Fig.5-3
WOODEN CONSTRUCTION
Roof Beam
Hanging Screw Bolts
Ceiling
Timber over the Beam
Put the square timber transversely over the roof beam, then
install the hanging screw bolts.
B
E. Connecting point of
Refrigerant Pipe
(D. gas side)
D. Connecting point of
Refrigerant Pipe
(E. Liquid side)
Drain Point
C
D
Hook
Содержание YN009GMFI22RPD
Страница 17: ...15 installation manual ...