![Phonowind Phono W-1.0 Скачать руководство пользователя страница 6](http://html1.mh-extra.com/html/phonowind/phono-w-1-0/phono-w-1-0_owners-manual_1553386006.webp)
WARNING:
Do not approach the generator in the weather of thunderstorm
2
14) Do not insatll the generator in the bad weather or when the wind speed
is over 5m/s
15) Phonowind must be installed in accordance with this manual and local
and national building codes. Failure to comply with the manual and local
codes will affect and possibly void your warranty.
16) Phonowind uses high voltage and is potentially dangerous. Be sure to use
all safety precautions at all times.
WARNING:
Do not change the battery connection wires when the generator,
controller and inverter work. Please turn off the generator, controller and inverter
before disconnect the battery connection wires.
WARNING:
Unloading resistance is the important control brake and overload
unloading protection component in the system and ensure that it connects the
controller effectively. Do not change the unloading resistance connection wires when
the generator, controller and inverter work.
The Requirement of Personnel
1) Only the people who have full civil capacities are allowed to do the related work.
2) Only the designated personnel who have trained by manufacturer, read and got a
good understanding about the manual, can do the installation and maintenance
work of generator.
3) The work high above the ground can only be done by the well-trained workers
4) There must be one experienced worker to supervise constantly if the workers who
are undergoing training want to do any operation on the generator.
5) At least two workers do the generator installation and maintenance work
simultaneously
6) The personnel's protection: to avoid being hit by the falling objects, the workers
must put on the safety helmets with locking belts when they are working around
the towers. And they must wear the life jackets if the generator is near to the water
sites.
Содержание Phono W-1.0
Страница 1: ...OWNER S MANUAL Installation Operation Maintenance...
Страница 19: ...15 Installation Flow Chart...
Страница 24: ...20 Step 1 Step 2 Step 3 B A A A...
Страница 25: ...21 Step 4 Step 5 Step 6 Overturn Overturn...
Страница 26: ...22 L1 L2 L3 L1 L2 L3 3mm...
Страница 29: ...25 Connections of Tail Rudder and Generator Step 1 Step 2 Step 4 Step 3...