Pipe Installation
Figure 9: Pipe Installation
Wiring Installation
Power, Alarm and Control Connections
Figure 10: Inside the Detector
Exhaust Pipe
Notes: a) All wiring should comply with
local requirements and regulations.
b) Loop wiring must observe the
recommendations of the panel
manufacturer
Notes:
- use the PipeIQ BOM Report to order the Pipe components
required to assemble the system
- use the PipeIQ Pipe Layout Report to assemble the pipe layout
Important: follow the Pipe Layout report as closely as practical.
- ensure Pipe Lengths are correct
- ensure Sampling Point holes are drilled at the stated positions
-
ensure Sampling Point Hole Size is as defined
The PipeIQ design is based upon the information provided to the designer - this is often incomplete and therefore
inaccurate.
If it is not practical to install the system as designed, stop work, record the issues taking care to measure the
changes required, then redesign the PipeIQ BEFORE proceeding
(Unequal Pressures)
(Equal Pressures)