ST-01 Speed gate, STD-01 Double-sided section
Note:
When it is impossible to use flexible conduit for cabling, then it is necessary to route DC and
CAN cables prior to the sections installation. These cables are located under the housing of
the
Slave
section central post (side of the section). To do so it is necessary to unpack the
Slave
section, dismantle the housing of the central post (see Fig. 19), take out DC and CAN
cables and disconnect them from the drive control board. There are numbers on the cut-off
ends of the core that correspond to the connection layout (Fig. 18).
6. Unpack
the
Master
section (box
№
1,
ST-01/M
). Do not work alone! Carefully take the section
out of the box by holding it by the top duct.
7. Unpack the section top covers (packed in a separate box).
8. Dismantle parts of the speed gate section as described:
Remove the central post cover plate (5) (Fig. 199, Sect. 8.9.1).
Dismantle the front panels of both side posts (8) (Fig. 20, Sect. 8.9.2). Prior to this -
disconnect the connection cable from the front-end indication block.
9. Install the speed gate section on the anchor sleeves. Do not work alone!
10. Route cables through the hole located in the base of the
Master
central post: from PS (16),
RC-panel (17), Fire Alarm device (18) and from the optional equipment. Route DC (19) and
CAN (20) cables from the
Slave
section (side of the section) or a flexible conduit for cabling.
11. Fix the section on the mounting surface by using eleven M10 bolts with washers. Align the
vertical position of the speed gate section with a level. Minimum angle measured from the
vertical of the section should not exceed 0.5º. It is allowed to use mounting gaskets.
Note:
Points 12-16 should be applied for
STD-01
double-sided section installation.
12. Unpack and install the double-sided section. Act as described in points 7 - 9 (for both sides of
the section). Place the double-sided section so its
Slave
side stands towards the installed
Master
section.
13. Take DC and CAN connection cables out of the central post of the double-sided section from
the
Slave
side (if they hadn’t been routed in the cable channel earlier). Lead them through the
hole that is located on the base of the post. Route cables with a flexible conduit to the
Master
section.
14. Route cables for controlling the second passage lane by using the hole located in the base
plate of the double-section central post (from the
Master
section side): from PS, from RC-
panel or ACS-controller, from the Fire Alarm device and from optional equipment. Route DC
(19) and CAN (20) cables from the
Slave
section (side of the section) or a flexible conduit for
cabling.
15. Align the vertical position of the double-sided section and fix it on the mounting surface by
using 14 M10 bolts with washers (see point 11).
16. Install other double-sided sections if needed (points 12 - 15).
17. Unpack and install the speed gate
Slave
section. Proceed as described in points 7 - 9.
18. Take DC and CAN cables out of the
Slave
section (if they hadn’t been routed in the cable
channel earlier). Lead them through the hole that is located in the post base plate. Route
cables with a flexible conduit to the
Master
section.
19. Align the vertical position of the section and fix it on the mounting surface (see point 11).
20. Connect cables to the control board of the first passage lane according to the speed gate
electric connection layout (see Fig. 9 and Fig. 18). The control board is located in the bottom
side of the
Master
section
central post.
Note:
DC (2) and CAN (4) cables should be connected to the
X5
terminal blocks of the
Master
section control board and to
X1
terminal blocks of the
Slave
section drive board in
accordance with the conduit marking (see Fig. 18).
25