11
G. Position the columns
Position the columns on the installation layout of base plate. Install the anchor bolts.
Check the columns plumpness with level bar, and adjusting with the shims if the
columns are not vertical. Do not tighten the anchor bolts
(See Fig.20)
.
Note:
Minimum embedment of Anchors is
110mm
.
Drilling
Cleaning
Bolting
11
0m
m
Width between
columns:2850mm
Overall width
:
3542mm
Adjusting with
the shims
56
10
55
Fig.20
Содержание 211SAC
Страница 1: ...TWO POST LIFT Model 211SAC Original ...
Страница 10: ...8 D Install parts of extension columns See Fig 16 Fig 16 24 26 20 42 25 37 41 ...
Страница 18: ...16 K Raise the carriages up by hand and make them be locked at the same level See Fig 26 Fig 26 ...
Страница 20: ...18 1 2 Connecting cable for high setting See Fig 28 Cable 1 Cable 2 Cable 1 High setting Fig 28 ...
Страница 22: ...20 M Install power unit See Fig 30 Fig 30 ...
Страница 30: ...28 IV EXPLODED VIEW Model 211SAC Fig 43 ...
Страница 36: ...34 4 5 POWER UNIT EXPLODED VIEW 81513003 81513004 220V 50Hz Single Phase 380V 50Hz Three phase Fig 48 ...
Страница 45: ...43 ...
Страница 46: ...44 Date 2021 01 Manual No 72221707 ...