Installation

Busbar

The Busbar Sections are secured to a framing system, 

such as Unistrut®, using the Hanging Brackets as shown 

below. The bar can be secured both on its fl at or on its 

edge.

Before lifting a Busbar Section, ensure that a detailed 

risk assessment is carried out for the lifting procedure 

being performed in that specifi c area.

Powerbar recommend that the hanging brackets must be 

mounted no more than 750mm / 30” from the center of the 

joints. Care is to be taken not to damage ends of the busbar 

during installation. 

Powerbar recommends the hanging brackets be mounted 

no more than 1.5 metres / 5’ apart.

 

Ensure that each section 

of busbar has at least one set of fi xing brackets fi tted and that 

the Busbar is level and plumb before fi nal tightening of all 

joints. Either drop rod or unistrut style hanging brackets are 

supplied depending on the client’s request. 

* Please note: Powerbar hanging bracket’s must be used. 

186mm

Max 750mm t

o

 fi

 rst 

hanger 

Max 750mm t

o

 fi

 rst 

hanger 

It is the responsibility of the support system supplier to ensure their 

system can safely support the weight of our product.

MAX

 DIST

ANCE

 1.5 M

TRS

Содержание iMPB

Страница 1: ...iMPB Installation Manual...

Страница 2: ...must be safely secured to the lifting apparatus before lifting Always check that the load does not exceed the safe working load of the lifting apparatus Ensure that equipment is used as per manufactur...

Страница 3: ...ts Care is to be taken not to damage ends of the busbar during installation Powerbar recommends the hanging brackets be mounted no more than 1 5 metres 5 apart Ensure that each section of busbar has a...

Страница 4: ...ar orientation and site conditions may restrict installers from adhering to this methodology In these cases installers must be cautious and ensure the joint pack is installed correctly Ensure all part...

Страница 5: ...ally the first component to be mounted on a run The entire route should initially be inspected for any obstructions before installation The box should be installed at the correct height in accordance...

Страница 6: ...omprise an arrangement of enclosure circuit breaker monitoring device on load isolator and safety interlocks which provide a unique set of safety features for installation and allow the tap off module...

Страница 7: ...ll connected load to the Busbar Trunking via tap offs for example should be isolated prior to energizing the bar The Main Supply switch to the Busbar is to be energized first The Protection Settings s...

Страница 8: ...66536 E I Engineering Corporation USA Manufacturing Location 400 Supreme Industrial Drive Anderson South Carolina 29621 Tel 1 864 375 1757 E I Engineering LTD European Manufacturing Location Ballydero...

Отзывы: