background image

15

9.  Part Replacement Procedures And 

Adjustments 

9.1  Ionizer  Wire(s)  Replacement                                                                                                                                

   Refer to Figure 14.  

1.  Remove damaged wire from each spring. 
2.  Replace spring if damaged or missing. 
3.   Loop one end of new wire over bottom spring. 

Pull top wire loop with pliers over top spring. 

4.   Wire should now be taut and centered. 

If replacement parts are not available, remove 
broken wires and tension springs from the ionizer 
section until parts are available. The unicell can be 
placed in service with missing ionizer wires. 

!

  NOTICE

Figure 14

Ionizer Wire Installation

9.3 Indicator Light Replacement 

1. Open the power pack enclosure lid cover. 

2.  Disconnect the red and black wires from the indicator light 

which is connected to wires “9” and “2”.  

3.   Remove indicator light installation nut. The indicator light 

located on each power pack enclosure is polarity sensitive. 

For proper operation, the two wires from the indicator light 

should be connected as follows, red wire connected 

to “9” wire from the power pack, black wire connected to 

“2” wire from the power pack. If the wires are reversed, the 

indicator light will not illuminate. The power pack indicator 

light circuit is DC voltage. 

4.  Install the replacement indicator light reversing 

the procedure. 

9.4  Component Access Door(s) Gasket 

Replacement

Should leakage occur an adjustment of the latch paws on the 

back of the door handles may solve the problem. Extreme care 

should be exercised in compressing door gasket beyond the 

design limits. Before adjusting for gasket deflection, check for 

the following: 

1. Door or cabinet damage. 

2. Deformed or torn gasket. 

3.  Leakage from some other source. Unicell components should 

be removed and replaced with great care to preserve gasket 

integrity. Should damaged gasket require replacement, 

contact Parker for the correct gasket material, BUNA-N (42-

0168) or EPDM (42-1503).

 

9.2  Door Feed-Thru Insulator(s) Replacement  

1. Place system off line. 

2. Open power pack enclosure lid cover. 

3.  Remove high voltage wire by removing #10-32 hex nut. 

4. Remove insulator retaining nut. 

5.  Open module door and remove the long screw from the 

insulator. 

6.  Remove the insulator from the interior of the module door. 

7. Clean silicone sealant from module door surface. 

8.  Install replacement insulator, reversing the procedure, and 

applying a thin coat of silicone sealant to base of insulator. 

 

Parker 

INLET PLENUM  MODULE  ODOR

  MODEL 

DOOR 

DOOR DOOR

PSG-11, -12, -13, -14 

5 FT 

7 FT 

12 FT

PSG-21, -22, -23, -24 

9 FT 

11 FT 

18 FT

PSG-32, -33, -34 

12 FT 

16 FT 

24 FT

PSG-42, -43, -44 

18 FT 

22 FT 

36 FT

PSG-52, -53, -54 

21 FT 

27 FT 

42 FT

Содержание SMOG-HOG PSG

Страница 1: ...SMOG HOG Electrostatic Air Cleaner Owner s Manual Model PSG...

Страница 2: ...ion avail able when contacting Parker Parker Order _________________________________________________________________ Unit Model ___________________________________________________________________ Unit...

Страница 3: ...2 3 Supports 3 2 3 1 Skidded Systems 3 2 3 2 Unskidded Systems 3 2 3 3 Utilities Drains 3 2 3 4 Ducting 3 3 Installation 4 3 1 Receiving Inspection 4 3 2 Unloading by Forklift 4 3 3 Unloading by Cran...

Страница 4: ...eck Power Pack Enclosure Indicator Light s 12 5 1 2 Unicell s Weekly Visual Inspection 12 5 1 3 Filters Drain Sumps and Access Door Gasket Inspection 12 5 1 4 Perform An In Place Cleaning Wash Cycle 1...

Страница 5: ...1 Tools Required 17 10 2 Perform Before Troubleshooting 17 10 3 Troubleshooting Procedure 17 10 4 Step 1 Checking the Power Pack 18 10 5 Step 2 Checking the Unicell Components 19 10 6 High Voltage Pr...

Страница 6: ...explosive Use non flammable cleaners Keep flammable materials and vapors such as gasoline away from unit The unit should be inspected frequently and contaminants removed to prevent excessive accumula...

Страница 7: ...ims any liability or responsibility for damage from fires or explosions regardless of origin Parker recommends that all APC dust collection equipment installation and application conform to any and al...

Страница 8: ...h is non lethal Unicell components are usually preceded and or followed by mesh filters to assure even distribution of air at low velocity Air movement is provided by a system blower located behind th...

Страница 9: ...r pack is self protecting against overloads e g dirty components short circuits in ionizer and cell circuits and is self regulating when the AC voltage supply varies from 90 to 132 VAC 1 4 2 Unicell I...

Страница 10: ...ng are general guidelines 2 1 Location Systems should be located as near as possible to the emission source but with consideration given to utility proximity and safe maintenance access Indoor locatio...

Страница 11: ...led by forklift truck but final placement may require a crane refer to unit System Layout Drawing for weights sizes and notes detailing responsibilities of the installing contractor 3 2 Unloading By F...

Страница 12: ...tem Installation If PSG installation is delayed for an extended period one month or more protect system components as follows 1 Store in a cool dry location Do not disassemble Do not re move component...

Страница 13: ...procedure until a 1 4 clearance is obtained between top place and housing 3 Check the level of the equipment The equipment may now be leveled by making small adjustments of individual isolators at the...

Страница 14: ...rmed by a qualified electrician in accordance with local electrical codes Disconnect electrical power before installing or servicing electrical components The PSG is manufactured per job specification...

Страница 15: ...ZER CELL FEED THRU INSULATOR ASSEMBLIES 2 37 0026 INSULATOR ONLY 2 6 37 0028 IONIZER STANDOFF INSULATOR 4 7 03 0559 IONIZER WIRE SPRING 20 8 03 0738 IONIZER WIRE 10 MIL SST 10 9 30 0387 CELL CONTACT S...

Страница 16: ...Tension The drive belt tension adjustment is critical within the first 24 hours of the system exhaust blower operation During this 24 hour period the initial stretch of the belt occurs which requires...

Страница 17: ...peed will decrease airflow CFM and current amperage To decrease speed open the variable pitch pulley from normal as in Figure 8A toward full open as in Figure 8C To adjust the variable pitch pulley 1...

Страница 18: ...media which does not support combustion PSG systems requiring an ETL listing will have potassium permanganate The odor control cabinet consists of a number of odor filters as dictated by size of the...

Страница 19: ...us panel or remote beacon or BMS Occasional arcing flashing of an indicator light is normal An established arcing condition or dead short condition continuous flashing of an indicator light or the ind...

Страница 20: ...etergent concentration in a mixture with water varies with the application from 1 1 to 25 1 parts water to parts detergent For any contaminant condition the best course is to use a cleaning solution p...

Страница 21: ...cement set of unicells and filter media 7 3 Automatic Parts Washers Certain commercially available units which are effective combine and automate the features necessary for effective cleaning includin...

Страница 22: ...l the replacement indicator light reversing the procedure 9 4 Component Access Door s Gasket Replacement Should leakage occur an adjustment of the latch paws on the back of the door handles may solve...

Страница 23: ...en power pack enclosure lid cover 3 3 Loosen 5 16 hex jam nut 9 then back off push rod extension 1 to end of threads 4 Close power pack enclosure lid cover listening for point where limit switch 4 is...

Страница 24: ...will decrease collection efficiency 2 There are run away voltages to the power pack requiring power pack replacement above 12 0 KVDC to the ionizer circuit and 7 5 KVDC to the collector cell circuit...

Страница 25: ...itch in the on position and engage the interlock switch Confirm 120 VAC to the power pack enclosure terminals not the power pack terminals 5 and 6 Verify the interlock switch operation 120 VAC to the...

Страница 26: ...igh voltage feed through insulator replace insulator Ionizer wires not taut contacting the ground plates Bent ionizer wire support bar contacting a grounded surface Bent ground plates contacting the i...

Страница 27: ...all outlet 6 Measure high voltage with the high voltage probe ionizer volt age should be 10 0 to 11 8 KVDC not to exceed 12 0 KVDC If ionizer voltage exceeds 12 0 KVDC the ionizer wires are moderately...

Страница 28: ...e 5 0 to 7 5 KVDC not to exceed 7 5 KVDC The collector cell will not maintain high voltages above 7 5 KVDC The collector cell will continuously arc Usually this condition is caused by a power pack abo...

Страница 29: ...ure indicator light is not illuminated Power pack enclosure toggle switch is in the off position Remove debris Power pack enclosure s push rod assembly is not properly adjusted Refer to Section 9 5 Po...

Страница 30: ...y 1 Unit Model Number nameplate 2 Unit Serial Number 3 Part Number or Part Description see illustrated parts 11 2 Returning Parts When returning parts directly to Parker call Customer Service at 1 800...

Страница 31: ...24 12 Power Pack Enclosure Assembly 16 17 12 13 15 35 4 28 26 29 34 19 22 18 24 25 23 1 20 21 31 30 27 31 1 32 33 8 1 5 7 6 2 3 9 10 11 14 POWER PACK ENCLOSURE ILLUSTRATION...

Страница 32: ...eed Through Insulator 2 19 30 0398 Round Head Screw 10 32 x 4 SST 2 20 30 0412 Lock Washer 10 EXT Tooth SST 2 21 30 0367 Fender Washer x 1 1 2 SST 2 22 35 0013 Spacer 2 23 30 0310 Pal Nut 5 8 16 2 24...

Страница 33: ...ced if necessary by the manufacturer trained and or certified agent A record of such inspection and cleaning shall be kept on the premises for inspection 7 Certificate of Approval number shall be plai...

Страница 34: ...or misuse misapplication or normal wear and tear e Equipment not properly installed operated and maintained under normal conditions and recommended applications As Buyers exclusive remedy for any def...

Страница 35: ...shooting effort details 5 Description of physical location and or environment details The Buyer shall cooperate with PARKER in its investigation and provide full information and documentation concerni...

Страница 36: ...rlands 31 76 508 5300 www parker com dhfns Hiross Zander Essen Germany 49 2054 9340 www parker com hzfd Padova Italy 39 049 9712 111 www parker com hzfd Engine Filtration Water Purification Racor Dews...

Отзывы: