Connect Rogowski coils to conductors
1.
Disconnect power to the BGS16 if possible.
If it is not possible to disconnect power, always treat the coil leads as
though they carry line voltages. Work on live panels must only be
performed by qualified personnel.
2.
Open the Rogowski coil by pinching the closing unit on the side of the connector.
3.
Position the coil on the conductor such that the
arrow on the connector faces
toward the load and away from the source
.
4.
Close the Rogowski coil and ensure the closing unit has clicked into place.
Connect Rogowski coil cables to CT leads
CT leads coming from the CT Interconnect Board will typically be labeled CT1, CT2, CT3,
etc. unless otherwise specified. Connect the Rogowski coil cable to the corresponding CT
lead using the quick connectors. The power monitor automatically detects the correct phase
once load is present. Current-only meters are not phase-specific.
The arrow on the coil
connector faces toward
the load and away from
the source.