1 3
Oracle Talari E100 Hardware Guide
Installing the APN Appliance
Rack Installation
Prior to installing the system in a rack, adhere to the following rack installation
guidelines:
Ensure that there is adequate airflow in the rack. Improper installation
or restricted airflow can damage the equipment.
You should leave at least 1U of vertical space between each system you install in
a rack.
The rack width and depth must allow for proper serviceability and
cable management.
Make sure the rack is properly secured to the floor or ceiling and grounded.
Always load the rack from the bottom up.
Load the heaviest component in the rack first.
Make sure the rack is level and stable before pulling a component out of the rack.
Do not move racks by yourself; at least two people are needed to move a rack
and to safely stage equipment.
Cables should be easily identifiable
.
LAN/WAN Connections
When connecting each Ethernet cable (LAN, WAN) to the appropriate connector on the
E100 APNA:
Position the cables carefully, so that they do not put strain on the connectors.
Organize cables in bundles such that cables do not intertwine.
Inspect the cables to make sure that the routing and bend radii are
satisfactory. Reposition cables, if necessary.
Install cable ties in accordance with site requirements.
Connecting Power to the Appliance
When connecting power to the E100 APNA:
Make sure the system is powered off using the power button on the rear of the
appliance.
Plug the AC power cord into the appliance.
Plug the AC power cord into an uninterrupted AC power source.