Delivery, interdepartmental transport and unpacking
Version 1.0.1 - 2021-1-28
26
Translation of original instruction
GB305D
EN
GB30
5D_GB
.f
m
3.2
Unpacking and connecting
The disc sander is mounted ready for operation. In order to obtain the correct direction of rota-
tion, the phase sequence must be changed if necessary. This is done at your three-phase con-
nection or - if equipped with it - at the three-phase connector by changing the phase sequence.
3.3
Scope of delivery
Check the disc sander immediately after delivery for transport damage, missing parts and loose
locking bolts. Compare the scope of delivery with the delivery note. Grinding wheels are availa-
ble in specialist shops or from our main catalogue.
3.4
Storage
ATTENTION!
Incorrect and improper storage might result in damage or destruction of electrical and
mechanical machine components.
Store packed and unpacked parts only under the intended environmental conditions.
Follow the instructions and information on the transport box.
Consult Optimum Maschinen Germany GmbH if the machine and accessories are stored for
more than three months or are stored under different environmental conditions than those spec-
ified here.
3.5
Set-up and assembly
3.5.1 Installation site requirements
Organise the working area around the grinding machine according to the local safety regula-
tions.
ATTENTION!
The disc sander should be firmly attached to the base. For this purpose there are holes
in the base to screw the disc sander to your worktable.
INFORMATION
In order to achieve high levels of functionality and machining accuracy, as well as a long ser-
vice life of the machine, the set-up location should meet certain criteria.