Once the actual application program in the PLC has been completed, and the DM settings have been
optimised to transfer only the data required for the application,
•
Read the actual value of the PLC scan time from AR27 with the PLC in Run/Monitor mode.
•
Calculate the C200HW-PRM21’s I/O refresh time as shown in paragraph 3-2-2, ‘PLC cycle time’.
•
By subtracting these two figures, calculate the time required for the PLC program plus the overhead for
servicing additional units and peripherals.
Only if the PROFIBUS-DP cycle is several times smaller than the time taken by the PLC p overhead,
choosing the asynchronous data exchange method will result in a consistent reduction of remote I/O response
time.
Asynchronous data transfer mode with PLC p overhead
≈
2 * PROFIBUS cycle.
This will result in irregular data transfer, but data is updated at least once per PLC cycle.
Содержание C200HW-PRM21
Страница 1: ...C200HW PRM21 PROFIBUS DP Master Unit OPERATION MANUAL Cat No W349 E2 2...
Страница 2: ......
Страница 3: ......
Страница 4: ......
Страница 5: ...C200HW PRM21 PROFIBUS DP Master Unit Operation Manual Produced May 2000...
Страница 6: ...iv...
Страница 8: ...vi...
Страница 12: ...x...
Страница 66: ...Debug mode Section 4 4 50...
Страница 98: ...Messages Section 6 4 82...
Страница 108: ...Maintenance Section 7 3 92...
Страница 110: ...94...
Страница 112: ...96...
Страница 116: ...100...
Страница 120: ...104...
Страница 124: ......
Страница 126: ...Authorised Distributor Cat No W349 E2 2 Note Specifications subject to change without notice Printed in the Netherlands...