Figure 45. LCD cable connection
3. Before attaching the LCD to the EVK using the foam tape, test that it is working as expected. Because you already
flashed the host-controller project, you can use the host-controller GUI for testing purposes. Apply power to the EVK
and then connect the Ethernet cable. The GUI will not boot if the Ethernet cable is not connected.
Figure 46. Testing the LCD panel
The LCD should display graphics as expected and the touch interface should be responsive. If there are glitches,
disconnect the power source and Ethernet and attach the LCD cables again.
4. After you successfuly test the LCD, attach it to the EVK permanently using foam tape.
7.3 Programming the TWR-KM3x board
The steps below show how to import, debug, and flash the Meter project (KM3x) for TWR-KM35Z75. You can follow the same
process for the TWR-KM3x board variant.
NXP Semiconductors
Board setup, wiring, and assembly
NXP EasyEVSE EV Charging Station Development Platform User Guide, Rev. 0, 18 March 2022