Operating Instruction and Documentation
Sprinter NT
- 27 -
Its important for the troublefree working that the base plate are clean and the guides
of the sliding block are clean and greased.
• Bore holes to fix the dowels through the borings of the base plate. Clean the holes
with pressure air. Put in the dowels.
Nussbaum Company demands LIEBIG safety dowels (german dowel
manufacturer) or equivalent dowels of other manufacturer but observe the
regulations.
• Dowel the lift on the ground.
• Tighten the Liebig-dowels with the dynamometric key (M = 50Nm)
Each dowel must be tightened with the demanded torque. Otherwise the normal
function of the lift can not guaranteed.
Observe the regualtions of the other dowel-manufacturer.
• Raise and lower the lift several times with load. Check the torque of the dowels and
check the hydraulic parts for tightness.
• If necessary equalize the lift again. (read the chapter 5.5)
• Mount the covers.
• Dowel the foot protection on the floor. Lower the lift in the lowest position. Position
the protection. The distance between the platform and the protection is approx. 10
mm. The protection must not touch the platform.
9.4 Extension of the hydraulic-hoses
• The hydraulics-hoses must be extended if necessary, must be tested afterwards,
whether the hoses were also assigned right.
Control:
Assumption: the hoses was connected right:
Raise the lift on approx. 500 mm.
After it open the screw A1 (equalisation) and the screw N1 (emergency lowering) of
the operating unit.
Effect:
no side of that lift subsides.
Assumption: the hoses became connected not right:
Raise the lift on approx. 500 mm.
After it open the screw A1 (equalisation) and the screw N1 (emergency lowering) of
the operating unit.
Effect:
one side that
lift subsides.
The assignment of the hydraulics-hoses is to be checked again.
• Close the crew A1 and the crew N1again.