OPI-POWER LIFT HDL 15000 - HDL 18000-V1.0-EN
51
• Tighten the anchor to the required torque (see
the conditions of the anchor manufacturer).
!
Each anchor must be tightened to the required
torque. Safe operation and stability of the lift are
not guaranteed with a lower torque.
•
If required, do a reset before first operation. (see
Section 6.3).
•
Raise the lift approx. 800 mm.
• Mount the lifting arm. Secure the bolts with the
locking rings.
• The lift must be moved to the “lift” and “lower”
end positions without a vehicle.
• The safety devices must be checked.
• Move the lift with the load into the end position
several times. (see Section 5.1).
• Check the hydraulic lines again for leak-tightness.
• Check the anchor fastenings again.
i
In case of malfunction, firstly inform customer
service.
8.2 Commissioning
i
Before commissioning, a single safety inspection
must be done (use the “single safety inspection”
form)
If the lift set up is done by a specialist (factory
trained assembler) then he can also do the safety
inspection. If the set up is done by the operating
company then a specialist must be tasked with the
safety inspection. The specialist confirms seamless
operation of the lift on the set up protocol for single
safety inspection and releases the lift for use.
i
After commissioning, the set up protocol must be
completed and sent to the manufacturer.
8.3 Changing the assembly location
To change the assembly location the pre-conditions
must be met according to the assembly guidelines.
The location change is to be done according to
the following sequence.
•
Move the lifting stage upwards to approx. 1,000
mm.
• Remove the tank covers
• Remove the lifting arm.
• Lower the lift to the lowest position.
• Disconnect power.
• Loosen base plate anchors.
• Transport the lift to the new assembly location.
• Assemble the lift according to the procedure
during assembly and anchoring before first com
-
missioning.
!
Use new anchors. The old anchors are no longer fit
for purpose!
i
Before re-commissioning, a safety inspection
must be done by a specialist (use the regular
safety inspection form)
Содержание HL2150.034-7016
Страница 2: ...2 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 4: ......
Страница 20: ...20 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 21: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 21...
Страница 22: ...22 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 23: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 23...
Страница 24: ...24 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 25: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 25...
Страница 26: ...26 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 27: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 27...
Страница 28: ...28 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 29: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 29...
Страница 30: ...30 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 31: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 31...
Страница 32: ...32 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN...
Страница 69: ......
Страница 70: ......
Страница 71: ...Made in Germany POWER LIFT HDL 15000 POWER LIFT HDL 18000 Made in Germany Spare parts list...
Страница 73: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 73 Cylinder assy 265HDL22000_1 27 03 2004...
Страница 74: ...74 OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN SPX Unit USA...
Страница 77: ...OPI POWER LIFT HDL 15000 HDL 18000 V1 0 EN 77 Hood 265HDL01032 15 03 2004...