20
NFS2-3030/E Installation Manual — P/N 52544:N1 07/18/2014
Installation
Mounting a Cabinet
3.3 Mounting a Cabinet
This section provides instructions for mounting the CAB-4 Series backbox to a wall. Follow these
guidelines when mounting the backbox:
•
Locate the backbox so that the top edge is 66 inches (1.6764 m) above the surface of the
finished floor.
•
Allow sufficient clearance around cabinet for door to swing freely. (See Section 2.4 “System
Cabinets”.)
•
Use the four holes in the back surface of the backbox to provide secure mounting (See
Figure 3.1).
•
Mount the backbox on a surface that is in a clean, dry, vibration-free area.
Remote Data Port devices
LCD-160 Manual
Printer or other output device(s)
Section 3.14 “Installing Printers”
Network devices
Noti•Fire•Net Version 4.0 & Higher Manual/High-Speed
Noti•Fire•Net Manual,
and/or Installation document for
specific device(s)
7.
Wire the Signaling Line Circuits
(Notification Appliance Circuits and
Initiating Device Circuits)
Section 3.15 “Wiring a Signaling Line Circuit (SLC)” and the
SLC Wiring Manual
8.
Calculate the proper battery rating.
Main Power Supply Manual
9.
Install main power supply & batteries in
separate enclosure. Run cable to main
& optional power supplies, DC power
outputs, relays, etc.
• Section 3.10 “Connecting Power Sources and Outputs”
• Section 3.11 “UL Power-limited Wiring Requirements”
WARNING:
DO NOT ACTIVATE POWER AT THIS TIME. DO NOT CONNECT BATTERIES.
Main power supply.
• Main Power Supply Manual
• BB-100/200 Cabinet Installation Instructions
Auxiliary power supply and/or
external battery charger
Auxiliary power supply manuals and/or battery charger
manuals. Note: If using multiple power supplies with one set
of batteries, refer to main power supply manual for
connection requirements.
10. Check that all mounting holes are secured to insure a proper Earth Ground connection.
11. Connect wire shielding to Earth Ground.
12. Remove insulator from lithium battery
on CPU
Section 3.5.4 “Memory-Backup Battery”
13. Apply AC power to the control panel by placing the external circuit breaker to the ON position.
Do NOT connect batteries until AC power is checked (see next step).
14. Check AC power.
Section 3.10.3 “Checking AC Power”
15. Connect the batteries using interconnect cable as described in power supply manual.
16. Install the dress panels, doors and
covers.
CAB-3/CAB-4 Series Cabinet Installation Document
17. Program the control panel.
Programming Manual.
18. Field test the system.
Section 5 “Testing the System”
Task
Refer to:
Table 3.1 Installation Checklist (2 of 2)
!