41
Commissioning
Nortec EL/RS Outdoor
2584597_B_EN_1705
6
Commissioning
6.1
General
The Nortec EL/RS Outdoor humidifier must be commissioned and operated only by personnel who are
well qualified and properly trained to commission the Nortec humidifier. It is the customer's responsibility
to verify the qualifications of personnel.
6.2
Commissioning
The unit must always be commissioned for the first time by a service technician from your Nortec rep-
resentative, or by personnel who are well trained and authorized by the customer. For the consolidated
installation checklist, refer to the
"Installation Checklist" on page v
The steps are in the following order:
1. Inspect the mounting of the outdoor steam humidifier.
2. Inspect the steam and condensate line connections.
3. Inspect the water and drain connections.
4. Inspect the electrical connections.
5. Inspect the external freeze protection system.
6. Flush the water supply and drain lines.
7. Make sure that the steam cylinder is seated properly in its base.
8. Configure the controls and the Nortec EL/RS Outdoor humidifier.
9. Wire the unit to a remote monitoring system, and verify that it is functional.
10. Conduct performance tests, including control and monitoring devices.
11. Fill out the commissioning protocol documents.
Содержание EL SERIES
Страница 10: ...6 Receiving and Storage 2584597_B_EN_1705 Nortec EL RS Outdoor This page intentionally left blank ...
Страница 16: ...12 Product Overview 2584597_B_EN_1705 Nortec EL RS Outdoor This page intentionally left blank ...
Страница 46: ...42 Commissioning 2584597_B_EN_1705 Nortec EL RS Outdoor This page intentionally left blank ...
Страница 58: ...54 2584597_B_EN_1705 Nortec EL RS Outdoor This page intentionally left blank ...