STARTUP PROCEDURES
The operator must make reference to Figure #1
(“Typical Nozzle Layout”) when following these
instructions. The configuration prior to startup
operations must be as follows:
·
All components have been visually checked
for proper connections. Corrective actions to
repair or adjust components must be
completed.
·
All supply and feed lines have been cleaned.
·
The on/off valve of the primary water pressure
control section is OFF.
·
Water at 25 psig pressure from the main
supply is ON.
·
The on/off valve of the primary air pressure
control section is OFF.
·
The air compressor is running and providing a
minimum of 90 psig.
·
The control panel switch is OFF.
·
The 24 Vac transformer is plugged into a 110
Vac source and the control panel power
indicator light is illuminating.
·
The humidistat is set at 100% relative
humidity.
COMPRESSED AIR SUPPLY
·
The clean out valves on the ends of the supply
pipes must be closed.
·
The on/off valve of the primary air pressure
control section is opened to the ON position.
The handle should be in line with the pipe (as
opposed to 90 degrees to it).
·
The control panel switch is turned to the ON
position.
- 14 -
Power
Off On
R
R
A I R
FOG
AFE Control
Air
Water
3/8" Compression
Fitting
Air
1/2" Compression
Fitting
Pilot In
1/4" Quick
Disconnect
Plastic Tube
Locking Nut
Bulk Head Union
On Plumbing Side
Of Unit
Tube Must Exceed End Of Sleeve
By a Min. Of 0.125" (3 mm)
For Copper Tubing
Replace Plastic Sleeve
With The Supplied
Brass Sleeve
Main
Air
Pilot
Signal
Figure #24
Four Octo Units With A Single Control Panel
15' ( 4.5 m)
Spray Pattern From
AFE Nozzle
48"
1219.2
m
m
Figure #25
AFE Octo Nozzle Plumes