3
To commission the gate, move the gate to approximately the
half way position, tighten the knurled wheel (Clockwise)
engaging the clutch just enough to drive but will still slip if the
gate hits something while travelling at high speed.
The clutch must be tightened up fully after commissioning.
Press the OPN button located under the dip switches to begin
opening cycle.
Ensure the direction the gate travels is in, accordance with the
opening and closing status LED’s, if not reverse two of the
motor wires at the inverter terminals.
Inverter settings can be adjusted via the keypad i.e. Opening
speed, closing speed and ramp times. Automation settings
operating modes are able to be adjusted via the CB6 board, refer
to manual for further instructions.
Once Inverter settings are appropriately set proceed to make
final adjustments to the limits. They need to be set so that they
switch prior to the gate reaching its full open and close,
initiating the ramp down period so the gate will slow down to
a complete stop at its final position. Once set, proceed with the
gate travel timing via the run/set switch, then firmly tighten
the clutch.