3.1.3 Electric connections
The system operates in parallel with the
filtration pump.
It is essential for it to operate at the same
time as the filtration system. A box
continuously connected to a separate socket
will annul the guarantee.
Before carrying out any electrical
work on the box, this connection requires
STERILOR Duo's power supply to be cut off at
the filtration box.
The connection is therefore made on
the filtration pump contactors in the existing
filtration box, according to the following
diagram:
Single-phase filtration box:
Three-phase filtration box:
3.2 Electrolysis cell
Dimensions:
Length 275 Height 180 mm Depth 152 mm.
Each cell has two PVC end fittings with
inside diameter of 50 and outside diameter of
63. These end fittings must be affixed to the
by-pass on the filtration circuit using PVC glue.
STERILOR Duo
STERILOR Duo
NEUTRAL
PHASE
Circuit
Contactor
EARTH
PUMP
SINGLE
Auto Op.
Forced Op.
Clock
Contactor
Circuit
NEUTRAL
PHASE
PUMP
Three phase
Forced Op.
Auto Op.
Clock