22
Zetasinter System
®
8.
Bubbler
Once the vacuum has been done 5 times (remembering to reinsert inert gas between each):
①
Remove the vacuum pump flexible air hose from the outlet flange. Then, connect the bubbler to the
outlet flange with the o-ring (may need grease). Remember to keep the inlet and outlet valves closed when
doing this.
②
Seal the connection by closing the clamp slightly.
③
Fill the bubbler with 70 mL of water (level at 110 mm height from the bottom).
④
Slowly
open the outlet valve (let the overpressure released to 0 bar) and set the flowmeter to 0.5 L/min
(or according to the filament guideline).
⑤
Set the heat treatment,
during it:
-
Adjust the water level to 110 mm every 48 hours to compensate the evaporation.
-
Inlet and outlet flange must be kept opened.
-
Stop the furnace (hold or stop states) if the pressure is higher than 0.2 bar (0.02 MPa) and/or the bubbler
is not bubbling.
1)
2)
3)
Maintenance
After every heat treatment:
-
Clean the binder residues with a degreaser and a bottle brush.
Содержание Zetasinter
Страница 12: ...12 Zetasinter System Specific settings Time Setting Heating programs saving ...
Страница 16: ...16 Zetasinter System Install the right flange inlet flange 1 2 3 4 5 Install the left flange outlet flange ...
Страница 26: ...26 Zetasinter System 11 Electrical schematic diagram 220V Electrical schematic diagram ...