7.2 OPERATIONS & FUNCTIONS

The solar system operator should become familiar with the following operating functions of the
ProStar controller. Refer to the Technical Specifications (section 10.0) for actual setpoints and
other parameter values.

100% Solid State:

All power switching is done with FETs. No mechanical relays are

used in the controller.

Battery Charge Regulation:

The ProStar is a PWM battery charger. See the next

section (8.0) for a description of battery charging.

Low Voltage Load Disconnect (LVD):

An automatic load disconnect protects the

battery from deep discharge. The load automatically reconnects when the battery
recovers. A 4-minute delay prevents false LVD disconnects.

Low Voltage Warning:

The red status LED will blink at low battery capacity to warn

of a possible LVD.

Parallel Controllers:

ProStar controllers work very well in parallel configurations. 

No blocking diodes are required. Each controller must have an independent and
separate solar subarray and a load that does not exceed the controller’s rating.

Auxiliary Generators:

Engine generators and other sources of power may be

connected directly to the battery for charging. It is not necessary to disconnect the
ProStar from the battery. However, do not use the ProStar to regulate these other
sources of power.

Noise:

The ProStar circuit minimizes switching noise and filters noise output. A

properly grounded system will also minimize noise. If noise is present in 
a telecom or radio load, refer to section 7.5 below.

7.3 PROTECTIONS

The ProStar is fully protected against system faults listed below. Recovery is automatic except
where noted below. Refer to sections 4.0 and 5.0 for fault indications.

• Solar short circuit and overload – fully automatic recovery

• Load short circuit and overload – after 3 automatic load reconnect attempts (10

seconds between each attempt), the fault must be cleared and the load must be
turned off or disconnected for 10 seconds or longer to restore power to the load
terminals. 

• Reverse polarity – fully protected except per Caution below

• Battery disconnected – the load is protected from voltage spikes

• High temperature – first the solar is disconnected, then the load will be

disconnected; auto reconnects

• High battery voltage – first the solar is disconnected, then the load will be

disconnected; auto reconnects

• Very low battery voltage – brownout protection, auto recovery into LVD state

• Battery select error – defaults to gel battery setting, flashes LEDs

• Temperature sensor failure – a remote probe failure defaults to the internal

temperature sensor, which defaults to a fixed 25°C if it fails

CAUTION:

One source of potential damage to the controller is a reversed 
battery polarity (+/–) together with a polarized or short-circuited load. 

RSPSupply  -  1-888-532-2706 -  www.RSPSupply.com

http://www.RSPSupply.com/p-8569-Morningstar-PS-30M-PG-Charge-Controller-12/24V-30A.aspx

Содержание ProStar PS-15

Страница 1: ...Voltage 12 24V 12 24V 48V Digital Meter Option yes yes standard Positive Ground Option no yes yes PROSTAR VERSIONS INCLUDED IN THIS MANUAL 1098 Washington Crossing Road Washington Crossing PA 18977 U...

Страница 2: ...136 6 01 153 4 14 105 3 50 89 inches mm 2 17 55 18 4 57 PROSTAR DIMENSIONS RSPSupply 1 888 532 2706 www RSPSupply com http www RSPSupply com p 8569 Morningstar PS 30M PG Charge Controller 12 24V 30A...

Страница 3: ...8 7 0 OPERATION 10 7 1 Operator s Tasks 10 7 2 Operations Functions 11 7 3 Protections 11 7 4 Inspection Maintenance 12 7 5 Special Features 12 8 0 BATTERY CHARGING INFORMATION 13 8 1 ProStar Charging...

Страница 4: ...ipment manuals before installing the solar system Observe ALL precautions when working with batteries and power electronics Fuses or DC disconnects may be required in the system These protective devic...

Страница 5: ...volts The controller selects 12 or 24 volts at start up 9 Observe the LEDs and digital meter if provided to confirm normal operation 10 It is recommended that the system be properly grounded 4 0 LED...

Страница 6: ...The push button next to the digital display can disconnect the Load or both Load and Solar A second push of the button will return the controller back to normal operation LOAD OFF A brief push of the...

Страница 7: ...detected To terminate the self test push the button The self test can be repeated to confirm the result Error List E0I Rotary switch battery selection failure E03 Voltage reference test failed circui...

Страница 8: ...efully observe the LEDs at each connection The LEDs will indicate proper polarity and a good connection 6 2 INSTALLATION STEPS Refer to the wiring connection diagram in section 3 0 STEP 1 Mounting Ins...

Страница 9: ...battery charging and control Both Sense wires must be connected A small wire size 18 AWG or larger can be used for the Sense because the current is very low Note that the middle 2 terminals are for s...

Страница 10: ...a 8 32 UNC or M4 screw 0 136 hole provided The Solar Battery and Load negative terminals are all connected together inside the ProStar per UL recommendations No switching or measurement is done in the...

Страница 11: ...ching noise and filters noise output A properly grounded system will also minimize noise If noise is present in a telecom or radio load refer to section 7 5 below 7 3 PROTECTIONS The ProStar is fully...

Страница 12: ...e temperature sensor and the green LED at J12 Instructions are provided with the remote probe The ProStar will automatically select the remote probe for battery temperature compensation if it is insta...

Страница 13: ...he battery life Gel cells are not equalized 8 2 SELECT BATTERY TYPE The Battery Type rotary switch allows selection of 1 of 3 charging algorithms These are broadly defined as the following battery typ...

Страница 14: ...nts are 2 times for 24V and 4 times for 48V 9 0 TESTING AND TROUBLESHOOTING 9 1 SELF DIAGNOSTICS If your ProStar includes the optional digital meter refer to section 5 4 for how to perform a self test...

Страница 15: ...and the battery This is a common cause of undercharging batteries See section 6 2 to connect the Battery Sense Check the condition of the battery Determine if the battery voltage falls at night with n...

Страница 16: ...the load will reduce the voltage at the load Check the LED indications on the ProStar If the red status LED is on the load has been disconnected due to low battery voltage LVD This is a normal protec...

Страница 17: ...R 11 4 12 6 R to Y BATTERY SETPOINTS 25 C Gel Sealed Flooded LVD 11 4 11 4 11 4 LVD reconnect 12 6 12 6 12 6 PWM regulation 14 0 14 15 14 4 Float 13 7 13 7 13 7 Equalization N A 14 35 14 9 15 1 HVD so...