background image

En-4

1   2   3   C

(MXZ-2E)
(MXZ-3E)
(MXZ-4E)

(MXZ-2E)
(MXZ-3E)
(MXZ-4E)

35 mm

15 mm

Lead wire

•  Be sure to attach each screw to its correspondent 

terminal when securing the cord and/or the wire to 

the terminal block.

•  Make earth wire a little longer than others. 

     (More than 35 mm)

•  For future servicing, give extra length to the con

-

necting wires.

<OUTDOOR UNIT>

Indoor/outdoor unit 

connecting wire

<INDOOR UNIT>

Terminal block

Terminal block

Terminal block

Terminal block for 

power supply

Terminal block

2-1. CONNECTING WIRES FOR OUTDOOR UNIT

1) Remove the service panel, top panel, front panel.

2) Loosen terminal screw, and connect indoor/outdoor unit connecting wire (B) from 

the indoor unit correctly on the terminal block. Be careful not to make mis-wiring. 

Fix the wire to the terminal block securely so that no part of its core is appeared, 

and no external force is conveyed to the connecting section of the terminal block. 

3) Firmly tighten the terminal screws to prevent them from loosening. After tightening, 

pull the wires lightly to confirm that they do not move.

4) Perform 2) and 3) for each indoor unit.

5) Connect power supply cord (A).

6) Connect the demand control transmission cable to the terminal block for DRED 

Interface.

7) Fix indoor/outdoor unit connecting wire (B) and power supply cord (A) with the 

cable clamps.

8) Fix the demand control transmission cable with the cable strap.

9) Close the service panel , top panel, front panel securely. Make sure that 3-2. PIPE 

CONNECTION is completed.

• 

After making connections between both power supply cord (A) and indoor/outdoor 

unit connecting wire (B), be sure to fix both cable and wire with cable clamps.

2.  OUTDOOR UNIT INSTALLATION

POWER SUPPLY

~/N 230 V 50 Hz

This unit has demand response capability which is compliant with AS/NZS 4755.3.1. To activate this function, you need to make a contract with remote 

agents such as electric supply company, then this unit should be connected to Demand response enabling devise (DRED). For further information, 

consult your dealer. This unit supports 3 Demand Response Modes (DRMs): DRM1, DRM2 and DRM3.

 CAUTION

• To prevent malfunction caused by noise, route the cord connecting this unit to DRED and the power supply cord as parallel as possible.

• Do not connect the demand control transmission cable to the terminal block for power supply.

• Do not pull, extremely bend or apply strong pressure on the wire to prevent failure.

• Do not screw DRED to outdoor unit.

• Do not put DRED in outdoor unit.

• Secure electrical wiring above clamp. 

• Do not get DRED wire caught in the service panel.

1 : DRM 1

2 : DRM 2

3 : DRM 3

C : COMMON

AS/NZS4755 

terminal block

Fig. 1

Fig. 2

Fig. 3

Fig. 4

Fig. 5

Fig. 6

3-1. FLARING WORK

Pipe diameter 

(mm)

Nut 

(mm)

A (mm)

Tightening torque

Clutch 

type tool 

 

for R410A

Clutch 

type tool 

 

for R22

Wing nut 

type tool 

 

for R22

N•m

kgf•cm

ø6.35 (1/4”)

17

0 to 0.5 1.0 to 1.5

1.5 to 2.0 13.7 to 17.7 140 to 180

ø9.52 (3/8”)

22

34.3 to 41.2 350 to 420

ø12.7 (1/2”)

26

2.0 to 2.5 49.0 to 56.4 500 to 575

ø15.88 (5/8”)

29

73.5 to 78.4 750 to 800

Tilted Uneven Burred

Good

No good

Burr

Copper pipe

Spare reamer

Pipe cutter

Smooth all 

around

Even length 

all around

Inside is shin-

ing without any 

scratches.

Flare nut

Die

Copper pipe

Clutch type

Flaring tool

Wing nut type

Copper 

pipe

1) Cut the copper pipe correctly with pipe cutter. (Fig. 1, 2)

2) Completely remove all burrs from the cut cross section of pipe. (Fig. 3)

•  Aim the copper pipe downward while removing burrs to prevent burrs from 

dropping in the pipe.

3) Remove flare nuts attached to indoor and outdoor units, then put them on pipe 

having completed burr removal. (Not possible to put them on after flaring work.) 

4) Flaring work (Fig. 4, 5). Firmly hold copper pipe in the dimension shown in the 

table. Select A mm from the table according to the tool selected.

5) Check 

•  Compare the flared work with Fig. 6.

•  If flare is noted to be defective, cut off the flared section and do flaring work 

again.

3.  FLARING WORK AND PIPE CONNECTION

Terminal block 

for DRED Interface

Front panel

Service panel

Terminal block 

for power supply

Cable strap

The tip should be 

pointed upwards.

Top panel

Содержание MXZ-2E52VAD2

Страница 1: ...ner MXZ 2E52VAD2 MXZ 3E54VAD2 MXZ 4E71VAD2 English Installation Manual For INSTALLER This manual only describes the installation of outdoor unit When installing the indoor unit refer to the installation manual of indoor unit ...

Страница 2: ...the system will cause mechanical failure system malfunction or unit breakdown In the worst case this could lead to a serious impediment to securing product safety n Do not discharge the refrigerant into the atmosphere If refrigerant leaks during installation ventilate the room If refrigerant comes in contact with a fire harmful gas could be generated n Check that the refrigerant gas does not leak ...

Страница 3: ...E INSTALLATION LOCATION Where it is not exposed to strong wind Where airflow is good and dustless Where rain or direct sunshine can be avoided as much as possible Where neighbours are not annoyed by operation sound or hot air Where rigid wall or support is available to prevent the increase of opera tion sound or vibration Where there is no risk of combustible gas leakage When installing the unit b...

Страница 4: ...or unit Units should be installed by licensed contractor according to local code requirements Outdoor unit installation Air inlet 169 500 Air inlet 4 10 21 Oval holes 396 Air outlet 840 Unit mm 361 330 1 6 DRAIN PIPING FOR OUTDOOR UNIT Please perform the drain piping work only when draining from one place 1 Choose one hole to discharge drain and install the drain socket 1 to the hole 2 Close the r...

Страница 5: ...ling devise DRED For further information consult your dealer This unit supports 3 Demand Response Modes DRMs DRM1 DRM2 and DRM3 CAUTION To prevent malfunction caused by noise route the cord connecting this unit to DRED and the power supply cord as parallel as possible Do not connect the demand control transmission cable to the terminal block for power supply Do not pull extremely bend or apply str...

Страница 6: ...ue 19 6 to 29 4 N m 200 to 300 kgf cm Gauge manifold valve for R410A Compound pressure gauge for R410A 0 101MPa 760 mmHg Handle Low Handle High Vacuum pump for R410A Close Open Hexagonal wrench 4 to 5 turns Stop valve for LIQUID Pressure gauge for R410A Precautions when us ing the control valve When attaching the control valve to the service port valve core may deform or loosen if excess pres sure...

Страница 7: ...rvice port of the stop valve on the gas pipe side of the outdoor unit 3 Fully close the stop valve on the liquid pipe side of the outdoor unit 4 Turn on the breaker 5 Start the emergency COOL operation on all the indoor units 6 When the pressure gauge shows 0 05 to 0 MPa Gauge approx 0 5 to 0 kgf cm2 fully close the stop valve on the gas pipe side of the outdoor unit and stop the operation Refer t...

Страница 8: ...BH79N583H01 HEAD OFFICE TOKYO BUILDING 2 7 3 MARUNOUCHI CHIYODA KU TOKYO 100 8310 JAPAN ...

Отзывы: