![MIOX RIO H1 Скачать руководство пользователя страница 51](http://html1.mh-extra.com/html/miox/rio-h1/rio-h1_installation-operation-and-maintenance-manual_1804804051.webp)
MIOX RIO Series Operators Manual
P/N: 102-00076-G
Page 50
During the startup from standby mode, the OSG also goes through a startup sequence. When
the low level switch in the oxidant storage tank is activated, the solenoid opens to allow water
flow for 60 seconds. Cell power is applied, the brine proportion pump comes on, and the OSG
should come into the operating window within five minutes.
If you have excessive stops and starts, the oxidant solution will be
diluted with start-up and shutdown flushes.
Brine Boost Pump Commissioning
The brine boost pump is electrically interlocked with the OSG. Once the OSG is in Run mode,
the pump will run. Once the pump is running, the back pressure valve must be set. Adjust
the pressure to a point that allows 3-5 PSI at the OSG. This is the optimum operating
pressure. Lower pressures cause strain on the OSG brine proportion pump and higher
pressure can cause bleed through of the brine proportion pump resulting in OSG faults.
Operation Controls
Modes of Operation
The modes of operation of the OSG are: Standby, Startup/Run, Self-Cleaning, Water Cycle,
Stop, Setup, Diagnostic, and Shutdown. Normal automated operation involves entering Run
mode to fill the oxidant tank. Once the oxidant tank is full, the OSG transition to Standby
mode. When the oxidant tank reaches a low level, the OSG will transition from Standby to
Startup to Run mode.
Standby Mode
The OSG is normally in Standby when the oxidant tank is full. The OSG can also be in
Standby if a Soft Fault condition is active and the Run/Stop switch is in the Run position.
If no Soft Faults are active, the OSG automatically transitions to Startup/Run mode
when the oxidant tank is low.
Startup/Run Mode
Startup mode verifies initial OSG condition, initiates and verifies cooling system function
and external Dilution Air system (if applicable) function. If functions are operational, the
cell is charged with water, power is applied, verified, and Run mode is entered.
Содержание RIO H1
Страница 1: ...RIO SERIES ON SITE GENERATOR M1 M5 H1 H5 Installation Operation and Maintenance Manual March 26 2019 ...
Страница 10: ...MIOX RIO Series Operators Manual P N 102 00076 G Page 9 Figure 2 RIO Series OSG Space Requirements ...
Страница 67: ...MIOX RIO Series Operators Manual P N 102 00076 G Page 66 Figure 34 Interface Board ...