DM17-01.01.08en
Light Commercial R410A on-off
164
9. Engineering of insulation
9.1 Insulation of refrigerant pipe
9.1.1 Operational procedure of refrigerant pipe insulation
Cut the suitable pipe → insulation (except joint section) → flare the pipe → piping layout and connection→
vacuum drying → insulate the joint parts
9.1.2 Purpose of refrigerant pipe insulation
During operation, temperature of gas pipe and liquid pipe shall be over-heating or over-cooling
extremely. Therefore, it is necessary to carry out insulation; otherwise it shall debase the performance
of unit and burn compressor.
Gas pipe temperature is very low during cooling. If insulation is not enough, it shall form dew and cause
leakage.
Temperature of gas pipe is very high (generally 50-100
℃
) during heating. Insulation work must be
carried out to prevent hurt by carelessness touching.
9.1.3 Insulation material selection for refrigerant pipe
The burning performance should over 120
℃
According to the local law to choose insulation materials
The thickness of insulation layer shall be above 10mm.If in hot or wet environment place, the layer of
insulation should be thicker accordingly.
9.1.4 Installation highlights of insulation construction
Gas pipe and liquid pipe shall be insulated separately, if the gas pipe and liquid pipe were insulated
together; it will decrease the performance of air conditioner.
Liquid pipe
Insulation meterial
Gas pipe
The insulation material at the joint pipe shall be 5~10cm longer than the gap of the insulation material.
The insulation material at the joint pipe shall be inserted into the gap of the insulation material.
The insulation material at the joint pipe shall be banded to the gap pipe and liquid pipe tightly.
The linking part should be use glue to paste together
Be sure not bind the insulation material over-tight, it may extrude out the air in the material to cause bad
insulation and cause easy aging of the material.
9.2 Insulation of drainage pipe
9.2.1 Operational procedure of refrigerant pipe insulation
Select the suitable pipe → insulation (except joint section) → piping layout and connection→ drainage test→
insulate the joint parts
9.2.2 Purpose of drainage pipe insulation
The temperature of condensate drainage water is very low. If insulation is not enough, it shall form dew and
cause leakage to damage the house decoration.
Содержание MUE-36HRN1-R1
Страница 13: ...Light Commercial R410A on off DM17 01 01 08en 13 Dimensions 3...
Страница 14: ...DM17 01 01 08en Light Commercial R410A on off 14 Service Space 4...
Страница 18: ...DM17 01 01 08en Light Commercial R410A on off 18 Wiring Diagrams 7 MCA3 12HRN1 Q1 MCA3 18HRN1 Q1...
Страница 22: ...DM17 01 01 08en Light Commercial R410A on off 22 Field Wiring 11...
Страница 29: ...Light Commercial R410A on off DM17 01 01 08en 29 4 Service Space 1000mm 1000mm 1000mm 1000m m...
Страница 35: ...Light Commercial R410A on off DM17 01 01 08en 35 6 Wiring Diagrams MCD 18HRN1 Q1 MCD 24HRN1 Q1...
Страница 36: ...DM17 01 01 08en Light Commercial R410A on off 36 MCD 36HRN1 R1...
Страница 37: ...Light Commercial R410A on off DM17 01 01 08en 37 MCD 48HRN1 R MCD 60HRN1 R...
Страница 41: ...Light Commercial R410A on off DM17 01 01 08en 41 10 Field Wiring MCD 18HRN1 Q1 MCD 24HRN1 Q1...
Страница 42: ...DM17 01 01 08en Light Commercial R410A on off 42 MCD 36HRN1 R1 MCD 48HRN1 R MCD 60HRN1 R...
Страница 55: ...Light Commercial R410A on off DM17 01 01 08en 55 6 Wiring Diagrams MTB 18HWN1 Q1 MTB 24HWN1 Q1...
Страница 56: ...DM17 01 01 08en Light Commercial R410A on off 56 MTI 36HWN1 R1 MTB 48HWN1 R MTB 60HWN1 R...
Страница 63: ...Light Commercial R410A on off DM17 01 01 08en 63 11 Field Wiring MTB 18HWN1 Q1 MTB 24HWN1 Q1...
Страница 64: ...DM17 01 01 08en Light Commercial R410A on off 64 MTI 36HWN1 R MTB 48HWN1 R MTB 60HWN1 R...
Страница 76: ...DM17 01 01 08en Light Commercial R410A on off 76 6 Wiring Diagrams MHG 24HWN1 Q1...
Страница 77: ...Light Commercial R410A on off DM17 01 01 08en 77 MHG 36HWN1 R1...
Страница 78: ...DM17 01 01 08en Light Commercial R410A on off 78 MHG 48HWN1 R...
Страница 79: ...Light Commercial R410A on off DM17 01 01 08en 79 MHG 60HWN1 R...
Страница 84: ...DM17 01 01 08en Light Commercial R410A on off 84 11 Field Wiring MHG 24HWN1 Q1 MHG 36HWN1 R1...
Страница 85: ...Light Commercial R410A on off DM17 01 01 08en 85 MHG 48HWN1 R MHG 60HWN1 R...
Страница 91: ...Light Commercial R410A on off DM17 01 01 08en 91 4 Service Space...
Страница 98: ...DM17 01 01 08en Light Commercial R410A on off 98 6 Wiring Diagram MUE 12HRN1 Q1 MUE 18HRN1 Q1 MUE 24HRN1 Q1...
Страница 99: ...Light Commercial R410A on off DM17 01 01 08en 99 MUE 36HRN1 R1 MUE 48HRN1 R MUE 60HRN1 R...
Страница 103: ...Light Commercial R410A on off DM17 01 01 08en 103 10 Field Wiring MUE 12HRN1 Q1 MUE 18HRN1 Q1 MUE 24HRN1 Q1...
Страница 104: ...DM17 01 01 08en Light Commercial R410A on off 104 MUE 36HRN1 R1 MUE 48HRN1 R MUE 60HRN1 R...
Страница 109: ...Light Commercial R410A on off DM17 01 01 08en 109 3 Dimensions Dimension Model W mm D mm H mm 24 500 315 1700 H W D...
Страница 110: ...DM17 01 01 08en Light Commercial R410A on off 110 4 Service Space...
Страница 112: ...DM17 01 01 08en Light Commercial R410A on off 112 6 Wiring Diagrams MFM 24ARN1 Q...
Страница 124: ...DM17 01 01 08en Light Commercial R410A on off 124 5 Wiring Diagrams MOBA30U 12HN1 Q MOBA30U 18HN1 Q MOCA30U 24HN1 Q...
Страница 125: ...Light Commercial R410A on off DM17 01 01 08en 125 MOD31U 36HN1 R MOU 48HN1 R...
Страница 126: ...DM17 01 01 08en Light Commercial R410A on off 126 MOUA 60HN1 R...
Страница 178: ...DM17 01 01 08en Light Commercial R410A on off 178 2 1 5 Display board of floor standing...