STEP 3:
Anchors are put onto the place where the tripod
barrier device will stand. Be sure that anchors are
balanced in both horizontal directions. The concrete is
applied according to the final foundation (pave).
NOTE
Setting the 0/0 position: It is demanded that the anchor
spacers are placed onto the final foundation of the
existing level - the upper surface of both anchors is on
the same level as ceramics, marble, final foundation, etc.
When the concrete is dry, the anchor spacers are
removed and can be used again.
STEP 4:
Attach the Tripod Turnstile on the anchors and
fix it with 6 x M8 nuts. Use M8 washers with external
diameter at least 24 millimetres or bigger. Washers are
not included with the anchors and must be bought
separately or they are provided by Metra when installing
the Tripod Turnstile. There are also rubber pads available
if anchors are slightly out of level and they are also used
for water insulation if needed. Contact Metra for more
details.
STEP 5:
Final position of devices should look like these.