3.3 Checking The Power Supply
METALMASTER machines are supplied wired ready to run. Check the specification plate on the
machine to confirm the correct voltage of the power supply.
The machine must be connected to the power by a qualified and licensed electrician. Warranty
could be voided if it is found that the connection was not carried out by a qualified electrician.
Start the pump by turning the key selector to the right.
Compare the direction of rotation of the motor. The blades need to rotate clockwise
If the direction does not match, stop the pump rotation by turning the key and make changes to
the wiring
3.2 Machine Leveling
To set your machine up so that it operates to optimum performance, apply the following procedure
After your panbrake has be anchored to a concrete slab floor, it then needs to be leveled. The level-
ing is performed using each of the screws on each pad.(Fig. 3.1). Loosen the hold down bolts and
place a level on the surface of the working table. Tolerances: 1000:0.30mm, for both axis.
Metal plates need to be placed under each jacking screw to distribute the load. Once level then
tighten the hold down bolts.
Metal Plate
Jacking Screw
The machine must not rest on supports other
than those defined in Fig. 3.1
Fig. 3.1