Metacon-Next B.V.
OHD-C EI(1) 60 / EI(2) 90 / EW 90 & OHD-C EI(1) 120
18-07-2022
User manual
art nr: 89022
Rev: 4
10
7
Installation preparation
Before the installation of the door can be started, the following items should be checked:
Before the installation can begin, the installation company must have familiarized
themselves with the contents of this user manual.
It is the responsibility of the installation company to be aware of the local regulations
concerning the installation of the door (e.g. Working Conditions Act).
Check the work area for accessibility and work space, then cordon off the work area.
Note the following points:
-
Check the clear width and height and the available side and top space, the
dimensions according to Technical Drawing are leading.
-
Check the mounting surface for obstructions.
-
Check that the surface is level for installation as indicated on the technical
drawing.
-
Check that the walls, floor and lintel are perpendicular and straight as shown
on the technical drawing.
-
Check that the correct electrical connections are present as shown on the
technical drawing.
-
Assess whether the substrate offers sufficient strength for the construction, if
in doubt contact the supplier.
Check all parts against the packing slip and/or order confirmation, and/or refer to the
list of all parts against the optional BOM (Bill Of Material) of the user manual.
7.1
Essential tools for installation
The required tools cannot be determined by Metacon-Next, as this depends on the
installation situation. It is up to the supplier and/or installation company to determine the
appropriate tools.