P 7
Please retain product label and instructions for future reference
15
23b
18
18
IMPORTANT :
Pre-drill before fixing screws.
15
15
15
Pre drill
hole
Step 11
Parts needed - No. 15 QTY 3
Align the Roof Purlin(
s
) (No.
17) into the cut out slots on each
gable top ensuring each purlin
interlocks the boards.
Secure the purlins at each
end by screwing through the bars
into the boards (ensure to pre-drill
to avoid the boards splitting) using
4x70mm screws per purlin.
*Please note:
The gable shown is for
illustrative purposes and may differ
in width from your choice in prod-
uct.
Nevertheless, despite any differenc-
es
the process of fixing the purlins
is the same.
70mm
screw
a
b
a
b
18
Step 12
Parts needed - No. 18 QTY 80
Place the first two roof
board’s (No. 18) onto the assembly
on each side, making sure the
boards are flush to the end of the
roof purlin. Once in position fix to
each purlin using 3x40mm screws.
Due to natural occurences of
wood shrinkage / expansion.
You maybe required to use
the provided spacers and
place a space of 2mm to
ensure every roof board
lines up with the truss’.
*Ensure the roof boards meet
at the top of the apex and leave
an overhang at the bottom.
Continue adding the roof boards
along the roof, fixing each one into
position using 3x40mm screws,
making sure that each board is
interlocked, flush at the bottom &
meet at the top of the apex.
The last board on each side
will overhang: Using a staight edge
and a pencil mark out a line as
a guide.
Cut along the pencil mark and
remove the excess. Place the
cut down board’s back onto the
roof and secure into place
using 3x40mm screws per
board.
*Please Note:
This image is for
illustrative purposes and may differ
from your choice in product.
Nevertheless the process of cutting
and fitting the last roof boards is the
same.
234x40mm Screws
40mm
screw
Pre drill
hole
*
Cut to fit
a
b
a
b
IMPORTANT :
Pre-drill before fixing screws.