background image

P 13

Step 28

Parts needed - No. 34 previously 

cut in to pieces in step 14.

            Position the four largest pieces 

of felt that you have cut (if you have 

not yet cut your felt please refer to 

Step 14) at the bottom of each side 

of the roof and fix with evenly 

spaced felt tacks. 

Make sure the felt 

overhangs by 50mm. Trim as 

required.

 

Take the 2300mm long strip 

of felt cut in Step 14 and place it at 

the top of the roof and fix using felt 

tacks. 

Make sure the felt overlaps by 

50mm. 

           Using the four strips of felt cut 

in Step 14 place them over each of 

the ridges in the roof and fix using 

felt tacks, avoid felt tack already on 

the roof.

Secure all of the felt  using felt tacks 

with even spaces of 100mm 

between each tack.

300x Felt tacks

C

B

A

A

B

C

1

2

3

4

34

Step 29

Parts needed - No. 19 QTY 4

 

 

   No. 20 QTY 2

Secure the Fascias 

(No. 19 & 20)

 

to the building using 3 screws 

per piece. 

The Fasicas for the side of the 

building should be secured last 

and will need to be cut to 

length.

*Ensure to screw through the 

fascia into the eaves frame 

behind avoiding any other 

screws.

24x30mm Screws

Pre drill 

hole

30mm 

screw

20

20

19

19

19

19

*

trim to fit

Step 30

Parts needed - No. 20 QTY 1

 

 

   No. 33 QTY 2

Before fitting the Roof Cap Fascia 

and the Finials to the Summer 

House, secure from underneath the 

two Finials 

(No. 33)

 to either each 

end of the Roof Cap Fascia 

(No. 20) 

by using one 50mm screw per 

Finial.

2x50mm Screws

20

33

33

Pre drill 

hole

50mm 

screw

Please retain product label and instructions for future reference

             

Содержание 03DTMBHP1206RFP

Страница 1: ...oisture loss Unfortunately these processes cannot be avoided but can be helped It is suggested that the outdoor building is sprayed with water during extended periods of warm sunshine and sheltered as...

Страница 2: ...996mm QTY 1 S1240 996mm Roof Bearer A 44x58x2211mm QTY 1 F4458 G 2251mm 2x32 CUTS 26 8 19 27 28 10 11 Eaves Frame 28x28x1805mm QTY 6 FS2828 1805mm 20 Building Content Roof Bearer B 44x58x528mm QTY 5 F...

Страница 3: ...g 5x30mm screws 5 x 30mm Screws Pre drill hole 30mm screw 21 21 24 24 SIDE VIEW 21 24 Step 2 Parts needed No 4 QTY 2 No 6 QTY 1 No 21 QTY 1 No 24 QTY 1 Lay all of the required parts on to a flat level...

Страница 4: ...nt Window Panel No 4 with 3x30mm screws per hinge Then fix the T hinges No 36 to the door with 3x30mm screws per hinge Repeat the process for the Master Door No 12 36 x 30mm Screws 36 36 Pre drill hol...

Страница 5: ...e drill hole 50mm screw 11 11 11 11 1 1 1 1 Step 6 Parts needed No 3 QTY 2 No 5 QTY 2 Fix the Side Window Panel No 3 and the Plain Panel No 5 togeth er by screwing through the fram ing using 5x50mm sc...

Страница 6: ...his is to be fitted to the opposite side 3 5 2 5 Step 8 Parts needed No 2 QTY 1 No 3 QTY 1 No 5 QTY 2 Place the two Plain Panels No 5 that were assembled with the Side Window Panel No 3 and the Back P...

Страница 7: ...Pre drill hole 50mm screw 4 4 5 5 Step 12 Parts needed No 4 QTY 2 Place the already assembled Door Panel No 4 6 12 13 22 25 into position and fix together with the two front plain panels No 5 3x50mm s...

Страница 8: ...de whilst you construct the roof 1600x200mm QTY 4 HANDLE WITH CARE 1 2 3 4 100mm gap between each panel 50mm overhang below each panel 50mm overhang below each panel 50mm overhang below each panel 260...

Страница 9: ...these panels have not been assembled yet please refer to step 13 Repeat this step for both sets of assembled roof panels No 8 9 10 8 10 9 Step 18 Parts needed No 14 QTY 1 No 16 QTY 5 Fix the Roof Bloc...

Страница 10: ...2 No 8 QTY 1 No 9 QTY 1 No 10 QTY 1 No 14 QTY 2 No 16 QTY 5 The use of a step ladder is essential to construct the roof To construct the Roof place the previously assembled in Step 19 6ft Roof Panel N...

Страница 11: ...the framing of the roof panels and that the pointed corners meet the line that was drawn in a Step 16 The underside of the roof should look as shown 10x60mm Screws Pre drill hole 60mm screw 15 15 15...

Страница 12: ...e screws go into the framing behind 24x40mm Screws Pre drill hole 40mm screw 22 22 22 22 22 22 Step 26 Fix the roofs to the panels below by screwing down through the roofs into the panel framing below...

Страница 13: ...felt using felt tacks with even spaces of 100mm between each tack 300x Felt tacks C B A A B C 1 2 3 4 34 Step 29 Parts needed No 19 QTY 4 No 20 QTY 2 Secure the Fascias No 19 20 to the building using...

Страница 14: ...g 5x30mm screws 5x30mm Screws Pre drill hole 20 33 33 20 33 33 30mm screw Step 32 Parts needed No 26 QTY 12 Fix the Cover Trims No 26 to each corner and over each join of the buiding with 3x30mm screw...

Страница 15: ...er hinge Repeat this step for both window sides of the building 20x20mm Screws Pre drill hole 20mm screw 31 35 31 Step 35 Parts needed No 29 QTY 1 No 30 QTY 2 On the internal of the doors fix the Towe...

Страница 16: ...that the edges are flush with the framing Fix with 4x30mm screws per strip 12x30mm Screws Pre drill hole 30mm screw 28 28 27 27 27 Step 38 Parts needed No 37 QTY 2 On the outside of the building fix t...

Страница 17: ...ng 1x10mm screw at each meeting point as shown in the diagram 24x20mm screws 8x10mm screws0mm screw20mm screw Pre drill hole 10mm screw 20mm screw 18 18 17 18 18 18 18 18 18 17 17 17 Please retain pro...

Страница 18: ...2 1 3 4...

Страница 19: ...REGISTER FOR YOUR ANTI ROT GUARANTEE TODAY PLEASE SCAN HERE 1 2...

Отзывы: