BX 4000 Sereies Quick Start Guide
Mellanox Technologies
Rev 1
7
Figure 4: Installation Kit Parts
Procedure
The following procedure can be done by one person, but inserting the gateway is much easier with two peo-
ple.
1. Place the ESD mat on the Floor where you will be working and put on the ESD strap. Make sure the
ESD strap is touching your skin and that the other end is connected to a verified ground.
Decide on Placement of the Gateway within the Rack
The gateway can be installed with either side even with the rack vertical support.
The distance between the rack and the door can be as little as 4 cm on one side of the rack and as much as 18
cm on the other side of the rack. Keep in mind that there can be as many as 10 cables for the MTB4010B
onnected to the gateway.
•
Do you want the connector side recessed in the rack to allow for a larger cable bending radius?
Figure 5: Which Side of the Rack Do You Want the Connectors?
2. Take the 2 rail slides and screw them to the gateway with the notched side up. Use eight of the
flat head screws for each rail slide. You can choose from two options for mounting the rail
slide; one option puts the end of the rail slide even with the end of the gateway and the second
•
Will the connector side be recessed past other equipment in the rack and will this be problematic?
Rail
Rail
slide