OM WGS-5
WGS 130A to 190A
25
Start-up after Extended Shutdown
1.
Inspect all equipment to see that it is in satisfactory operating condition.
2.
Remove all debris that has collected on the surface of the condenser coils (remote
condenser models) or check the cooling tower, if present.
3.
Open the compressor discharge valves until backseated. Always replace valve seal
caps.
4.
Open the manual liquid line shutoff valves.
5.
Check circuit breakers. They must be in the OFF position.
6.
Check to see that the circuit switches CS1 and CS2 and the unit control switch S1 are in
the OFF position.
7.
Close the main power disconnect switch. The circuit disconnects switches should be
off.
8.
Allow the sump heaters to operate for at least 12 hours prior to start-up.
9.
Start the chilled water pump and purge the water piping as well as the evaporator in the
unit.
10.
Start the system auxiliary equipment for the installation by turning on the time clock,
ambient thermostat and/or remote on/off switch.
11.
Check that the MicroTech II controller is set to the desired chilled water temperature.
12.
Switch the unit circuit breakers to ON.
13.
Start the system by setting the system switch S1 and the circuit switches to ON.
!
CAUTION
Most relays and terminals in the control center are powered when S1 is closed and the
control circuit disconnect is on. Therefore, do not close S1 until ready for start-up or serious
equipment damage can occur
.
14.
After running the unit for a short time, check the oil level in the compressor oil sight
glass and check the liquid line sight glass for bubbles.