KIT LANDING ON ROOFS AND COVERINGS
Mobile towers can also be used for landing on roofs and roofs, in the configurations indicated below,
with the appropriate landing kit.
The landing kit consists of two brackets for the safe locking of the short toe boards and 2 steel rods with
anti-slip device at the ends.
CAUTION:
Access to high-altitude floors is allowed only if suitable fall protection is guaranteed on these (parapets,
lifeline ...);
The mobile tower used to land at height must necessarily be used anchored to the wall, even if it is
a mobile tower with wheels compliant with the EN 1004 standard; In any case, compliance with the
maximum open spaces permitted by legislation must be guaranteed (Legislative Decree 81/08):
•
The distance between the walkway of the scaffolding and the landing point (building) must not
exceed 20 cm;
•
The maximum height difference between the walkway of the scaffolding and the landing surface
must not exceed 16 cm
If necessary, correct the height of the scaffolding only using the methods indicated in the manual
mentioned above;
Landing kit can only be used for the SYSTEM model
H max scaffolding m
3,50
5,00 6,50 8,00 9,50 11,00 12,50 14,00 15,50 17,00
H max work platform m 2,20
3,70 5,20 6,70 8,20
9,70 11,20 12,70 14,20 15,70
INSTRUCTIONS
1) Assemble the scaffolding in the desired configuration complete with all elements.
2) Install the parapet bars supplied with the kit on the side opposite the landing one;
3) Before use, anchor the scaffolding to a stable fixed structure every 2 rises.
4) The operator placed on the work surface near the landing, equipped with a suitable anti-fall sy-
stem anchored correctly, can then proceed with the disassembly of the long toe board placed on the
landing side, with the installation of the locking kit of the short toe boards, and then removal of the
batten and the bracing rods placed on the access side;