JIB SAFETY INFORMATION
1.
Ensure the proper jib mode is selected in the RCL.
2.
The anti-two block (A2B) switch weight and cord must
be attached to the jib when deployed.
3.
Do not lift the load with the main boom when the jib is
pinned on the tip of the main boom.
4.
Operate with jib by radius when main boom is fully
extended. If necessary, increase boom angle to maintain
loaded radius.
When radius is between points listed on capacity chart,
the load shown at the next longer radius shall be used.
5.
Operate with jib by boom angle when main boom is not
fully extended. Do not exceed rated jib capacities at any
reduced boom lengths.
When angle is between points listed on capacity chart,
the load shown at next lower boom angle shall be used.
6.
Ensure jib is stowed correctly (Figure 4-3):
a.
Removal of right side attachment pins (6), without
proper installation of stow pin (1) and jib swing pin
(5), may allow jib to fall off.
b.
Extending boom with jib stowed and failure to
remove right side attachment pins (6), will damage
unit upon extension.
7.
Only swing jib into working or stowed position when
boom is horizontal, stow pin (1, Figure 4-3) and jib swing
pin (5) are removed and right side attachment pins (6)
are in place. Jib could swing uncontrollably if boom is not
horizontal.
8.
Crane shall be fully set up according to proper set-up
procedures outlined previously when stowing or
unstowing jib.
9.
Operate boom and turn functions very slowly and
carefully when using jib since extension can increase
boom length by 50%.
10.
The area where jib swings around must be clear of
obstructions, personnel and power lines when stowing
and unstowing jib.
11.
Use safety glasses when installing pins with hammer.
12.
Do not extend/retract boom unless boom is horizontal
when stow pin (1, Figure 4-3) and jib swing pin (5) are
removed during stowing or unstowing procedures.
13.
Always put spring clips in pins to ensure that they will
stay in place.
14.
When the jib is stowed, the boom can not be fully
retracted if a boom tip attachment option is installed.
Also, on manually extendable jib options:
1.
Jib retaining pin (9, Figure 4-3) must always be installed
when operating.
2.
All swing around (stow and unstowing) operations shall
be done with jib retracted and pinned.
3.
Extendable section may slide out of 1
st
section jib when
jib retaining pin (9, Figure 4-3) is removed. Keep
personnel clear of area.
ERECTING AND STOWING THE JIB
General Warnings
NOTE:
Tag line used in these procedures is to control the
movement of the jib.
DANGER
To prevent serious injury or death, always wear personal
protective equipment; i.e., a hard hat, eye protection,
gloves and metatarsal boots.
DANGER
Boom angles are used to control speed at which jibs
swing during erecting and stowage. Improper boom
angles will cause uncontrollable swing speeds of jib.
DANGER
Before attempting to erect or stow the jib; read and strictly
adhere to all danger decals installed on the boom/boom
nose, jib, and stowage brackets.
Содержание National Crane NBT50 Series
Страница 1: ...Operator Manual National Crane NBT50 Series ...
Страница 2: ......
Страница 10: ...TOC 6 TABLE OF CONTENTS OPERATOR MANUAL NBT50 THIS PAGE BLANK ...
Страница 12: ...INTRODUCTION OPERATOR MANUAL NBT50 1 2 Published 03 23 2018 Control 243 14 FIGURE 1 1 7650 66 ...
Страница 50: ...2 36 Published 03 23 2018 Control 243 14 SAFETY PRECAUTIONS NBT50 OPERATOR MANUAL 8496 1 FIGURE 2 6 ...
Страница 82: ...CONTROLS AND OPERATING PROCEDURES OPERATOR MANUAL NBT50 3 22 Published 03 23 2018 Control 243 14 FIGURE 3 14 ...
Страница 134: ...MAINTENANCE CHECKLIST OPERATOR MANUAL NBT50 6 12 Published 03 23 2018 Control 243 14 THIS PAGE BLANK ...
Страница 157: ......
Страница 158: ......