NATIONAL CRANE
Published 03-23-2018 Control # 243-14
4-19
NBT50 OPERATOR MANUAL
SET-UP
4
b.
Press and hold the left and right Counterweight
Removal Cylinder Lower Buttons.
c.
Release the left and right Counterweight Removal
Cylinder Lower Buttons when cylinders are at the
proper position to pin the counterweight to the
cylinders.
If cylinders and counterweight do not vertically align,
return to cab and swing superstructure until
alignment is achieved.
NOTE:
The cylinders can rotate axially when no
counterweight is installed, causing the cylinder pin
holes to not align with holes in counterweight. If this
occurs, rotate cylinder rod using your hand or
counterweight pin.
9.
Attach Removable Counterweight to cylinders using
pins (5, Figure 4-12).
10.
Using Counterweight Switch Panel, fully raise
Counterweight Removal Cylinders by doing the
following:
a.
Press and hold a Power Button.
b.
Press and hold the left and right Counterweight
Removal Cylinder Raise Buttons.
c.
Release the left and right Counterweight Removal
Cylinder Raise Buttons when the cylinders are at
the fully raised position.
NOTE:
If top counterweight hits wear pads on the
superstructure when raising, swing crane to re-
align counterweight to mounting lugs, lower
counterweight back down onto mounting lugs on
carrier deck to realign counterweight on cylinder
pins, then raise counterweight again.
11.
Secure Removable Counterweight to left and right sides
of superstructure using pins (4, Figure 4-12).
NOTE:
It may be necessary to jog the cylinders up and
down to install pins.
12.
Slightly lower left and right cylinders to relieve the weight
of the counterweight from the cylinder pins.
Stowing the Counterweight
1.
Position crane on a firm, level surface.
2.
Fully extend and set the outriggers, then level the crane
(see
3.
Set display in Operator’s Console to the
RCL Operating
Mode Screen (Figure 4-11) (see
).
4.
While watching the display, rotate superstructure until
Counterweight Removal Slew Position Indicator (yellow
arrows) (1, Figure 4-11) appears in the display, which
indicates the rear of the superstructure is nearly directly
FIGURE 4-13
7868-01
7868-02
Counterweight Switch Panel
1
Power Buttons
2
Right Cylinder Raise Button
3
Left Cylinder Raise Button
4
Right Cylinder Lower Button
5
Left Cylinder Lower Button
6
Panel Power Indicator (LED)
1
2
4
3
1
5
6
Содержание National Crane NBT50 Series
Страница 1: ...Operator Manual National Crane NBT50 Series ...
Страница 2: ......
Страница 10: ...TOC 6 TABLE OF CONTENTS OPERATOR MANUAL NBT50 THIS PAGE BLANK ...
Страница 12: ...INTRODUCTION OPERATOR MANUAL NBT50 1 2 Published 03 23 2018 Control 243 14 FIGURE 1 1 7650 66 ...
Страница 50: ...2 36 Published 03 23 2018 Control 243 14 SAFETY PRECAUTIONS NBT50 OPERATOR MANUAL 8496 1 FIGURE 2 6 ...
Страница 82: ...CONTROLS AND OPERATING PROCEDURES OPERATOR MANUAL NBT50 3 22 Published 03 23 2018 Control 243 14 FIGURE 3 14 ...
Страница 134: ...MAINTENANCE CHECKLIST OPERATOR MANUAL NBT50 6 12 Published 03 23 2018 Control 243 14 THIS PAGE BLANK ...
Страница 157: ......
Страница 158: ......